H P Construction & Engineering Pte Ltd v Mega Team Engineering Pte. Ltd.

High Court (Appellate Division)

[2024] SGHC(A) 5 · AD/CA 120/2023 · cites 10 cases (8 Singapore, 2 foreign)

The question

Is the first day excluded when counting the seven days to lodge a payment adjudication application?

The answer

Yes. The Appellate Division held the seven-day period excludes the day the entitlement arises, so the application lodged on 6 July 2023 was in time, and dismissed the appeal.

Step 1: What happened

H P Construction & Engineering Pte Ltd (HP) engaged Mega Team Engineering Pte Ltd (MT) to supply labour under a sub-contract on a building project. MT served a payment claim on 30 May 2023. HP had to give a payment response by 20 June 2023 but did not. The seven-day dispute settlement period under s 12(6) of the Building and Construction Industry Security of Payment Act 2004 (SOPA) ran from 21 June to 27 June 2023, and still no response came. MT lodged Adjudication Application No. SOP/AA 150 of 2023 on 6 July 2023, and the adjudicator issued a determination on 21 August 2023.

HP applied in HC/OA 867/2023 to set aside the determination. Philip Jeyaretnam J dismissed the application on 9 October 2023. On appeal to the Appellate Division in Civil Appeal No 120 of 2023, HP pressed one point only: that the application should have been lodged by 5 July 2023 and was a day late. The facts were undisputed, and 29 June 2023 was a public holiday, which the SOPA does not count as a day.

Step 2: What the court had to decide

  1. Whether the day on which the entitlement to make an adjudication application first arises is counted in the seven-day period under s 13(3)(a) of the SOPA
  2. Whether s 50(a) of the Interpretation Act 1965 applies to the computation of that period
  3. Whether the purpose of the SOPA, industry guidance or earlier cases supported counting that first day

Step 3: How the court reasoned

The court first rejected a suggested reading under which MT could not apply until a day after the dispute settlement period ended. Under s 12(2) the entitlement arose as soon as that period ended on 27 June 2023, so MT could apply from 28 June 2023.

The key words of s 13(3)(a) require an application within 7 days after the entitlement first arises, not after the end of the dispute settlement period; these are different dates. Section 50(a) of the Interpretation Act excludes the day of the triggering event when computing a period of days, and HP did not dispute that this supported MT. The same rule exists at common law, as explained in Suresh s/o Suppiah v Jiang Guoliang [2016] 4 SLR 645, which also holds that the law does not count fractions of a day. The SOPA was drafted against that background and shows no contrary intention. HP's attempt to split 28 June 2023 at midnight was described as a desperate argument.

On purpose, the court held it was a stretch to say an extra day defeats the aim of fast adjudication; the text was neither ambiguous nor absurd, so extraneous material was not needed. Other SOPA timelines do not all follow seven-day multiples. The Building and Construction Authority guide and the Singapore Mediation Centre checklist wrongly counted from the end of the dispute settlement period and carried no weight against the statutory text. The cases HP cited had not argued the point.

From the judgment

“The attempt to split a day was a desperate argument which flew in the face of the point made by the court at [26]–[28] and [56] of Suresh that there is a general principle of law that the law does not take into account fractions of a day.”

[2024] SGHC(A) 5 at [39]

Step 4: The order

The Appellate Division dismissed the appeal with costs fixed at $30,400 inclusive of disbursements. It held that the seven-day period excludes the day the entitlement arises, so the adjudication application lodged on 6 July 2023 was in time.

The order in the court's words

Appeal dismissed

“We dismissed the appeal with costs fixed at $30,400 inclusive of disbursements.”

Source: [2024] SGHC(A) 5, High Court (Appellate Division), decided 15 February 2024. Read directly from the judgment.

Terms in this case

Security of payment
The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.
Adjudicator
Under Singapore's security of payment law for the building industry, the person appointed to decide a payment dispute quickly between parties to a construction contract, mainly on documents and within short fixed time limits.
Payment claim
A claim for a progress payment that a contractor or supplier serves under Singapore's security of payment law for the building industry. It starts the statutory process, and the other party must answer with a payment response within set time limits.
Adjudication determination
The decision of an adjudicator on a payment claim under Singapore's security of payment law for the building industry. It must be paid promptly, but the underlying dispute can still be finally decided later in court or arbitration.

Court record

Key facts

Court High Court (Appellate Division)
Decided
Judges Kannan Ramesh, See Kee Oon, Woo Bih Li
What the case was about Statutory Interpretation, Building and Construction Law
Outcome Appeal dismissed

Source: [2024] SGHC(A) 5, High Court (Appellate Division), decided — eLitigation. Updated .

Judges

Parties

  • H P Construction & Engineering Pte Ltd Appellant
  • Mega Team Engineering Pte Ltd Respondent

Counsel

Counsel for the appellant
  • LIMN Law Corporation Firm
  • John Lim Kwang Meng
  • Ng Kai Ling
Counsel for the respondent

Statutes cited

Cases cited (10)

SG (3)
SLR (5)
  • [2014] 3 SLR 264
  • [2015] 5 SLR 852
  • [2016] 4 SLR 645
  • [2017] 1 SLR 373
  • [2017] 2 SLR 850
UK (2)
  • [1913] 2 KB 549
  • [1961] 2 QB 135

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Referenced in

Statutes interpreted in this judgment

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC(A) 5)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer