Foreland Singapore Pte. Ltd. and another v Ig Asia Pte. Ltd.
[2024] SGHC 179 · HC/S 369/2022 · cites 17 cases
Could a broker reverse clients' closing trades under its force majeure clause after the exchange cancelled them?
No. The High Court held the clause let the broker withhold payment but gave no power to reverse the trades; that breach caused no loss, so it dismissed the substantive claim and awarded each client nominal damages of $1,000.
Step 1: What happened
Foreland Singapore Pte Ltd and Foreland Holdings Co Ltd (together, Foreland) traded nickel contracts for difference (CFDs) over the counter with IG Asia Pte Ltd (IGA) under IGA's standard Margin Trading Customer Agreement (MTCA). IGA priced the CFDs off the London Metal Exchange (LME) three-month nickel price and hedged its exposure on the LME through another IG Group company.
After an extraordinary surge in nickel prices, Foreland closed all its open nickel positions on 8 March 2022, and its account statements showed the resulting profits. That day the LME suspended nickel trading and cancelled all trades executed on or after 00:00 UK time on 8 March 2022. Foreland asked to withdraw $6,636,840.10 and $11,874,152.84. IGA did not pay; instead it reversed the closing trades by opening mirror positions, raised margins and later force-closed those positions. In Suit No 369 of 2022 Foreland claimed $9,653,223.79 and $12,944,800.22, or damages.
Step 2: What the court had to decide
- Whether Foreland was insulated from the LME suspension and reversal because it traded with IGA over the counter.
- Whether the suspension and reversal was a Force Majeure Event entitling IGA to withhold payment and to reverse the closing trades.
- Whether the Unfair Contract Terms Act, the account statements or Term 10(4) affected IGA's position.
- Whether Foreland suffered any loss from the wrongful reversal of the closing trades.
Step 3: How the court reasoned
The court held that trading over the counter did not shield Foreland from events on the LME. The CFD prices were derived from LME prices, as the MTCA and product details stated, and IGA's model depended on hedging on the LME, where the suspension left the day's hedges unmatched. Foreland knew or ought to have known this. The court preferred IGA's expert, finding Foreland's expert lacked relevant expertise.
The suspension and reversal fell within Term 23(1)(b) and (c) of the MTCA. Under Term 23(2)(c), IGA could suspend or modify only terms that the event made it impossible or impracticable for it to comply with. The event did so for the payment obligations in Terms 7(13) and 7(14), because the trades' basis in the underlying market had been retroactively annulled, so IGA could refuse payment of profits arising after 00:00 GMT on 8 March 2022. But Term 4(7), on which IGA relied to reverse the trades, imposed no obligation and so could not be modified under Term 23(2)(c). The reversal was therefore a breach.
The Unfair Contract Terms Act did not apply because acting within the force majeure clause was neither a breach nor an unexpected performance, and the parties were sophisticated. Term 10(4) was pleaded only if there was no Force Majeure Event. Had a power to reverse existed, the account statements would not have bound IGA because Term 14(7) bound only the client, and IGA's method of reversal left Foreland in the same economic position.
On remedies, Foreland's entitlement to the additional notional profits had already been extinguished when IGA validly modified its payment obligations, before the reversal. The breach was actionable per se, so nominal damages followed under Biofuel.
“While it is right for IGA to have refused to pay Foreland upon the execution of the FCTs, it is not correct for it to have also reversed the FCTs.”
[2024] SGHC 179 at [106]
Step 4: The order
Goh Yihan J dismissed Foreland's substantive claim. IGA was entitled to withhold payment under the force majeure clause but had no contractual power to reverse the closing trades, and that breach caused Foreland no loss, so each plaintiff was awarded only nominal damages of $1,000. Costs were to be submitted if not agreed.
Terms in this case
- Nominal damages
- A small sum awarded where a legal right has been infringed, such as by a breach of contract or a tort actionable without proof of loss, but the claimant has not proved any real loss.
- Breach of contract
- A failure, without lawful excuse, to perform a contractual obligation as and when it is due. Every breach gives the innocent party a right to damages; a sufficiently serious breach may also allow it to end the contract.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Goh Yihan |
| What the case was about | Contract, Banking |
Source: [2024] SGHC 179, High Court, decided — eLitigation. Updated .
Judge
- Goh Yihan Delivered the judgment
Parties
- Foreland Holdings Co., Ltd. Plaintiff
- Foreland Singapore Pte. Ltd. Plaintiff
- IG Asia Pte Ltd Defendant
Counsel
- DOP Law Corporation Firm
- Wong Tan & Molly Lim LLC Firm
- Lim Haan Hui
- Ling Daw Hoang Philip
- Low Ziron
- Ong Mung Pang David
Cases cited (17)
- [1999] 1 SLR(R) 945
- [2005] 1 SLR(R) 661
- [2005] 2 SLR(R) 509
- [2006] 4 SLR(R) 273
- [2006] 4 SLR(R) 308
- [2007] 4 SLR(R) 413
- [2008] 3 SLR(R) 1029
- [2011] 2 SLR 106
- [2013] 4 SLR 193
- [2016] 1 SLR 1069
- [2017] 1 SLR 219
- [2018] 1 SLR 170
- [2018] 2 SLR 199
- [2022] 1 SLR 302
- [2023] 3 SLR 1130
- [2023] 5 SLR 513
- [2024] 2 SLR 1
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Does a seller's part in a circular commodity trade make it liable to the bank that financed the buyer?
High Court · 5 June 2024 · [2024] SGHC 145 -
Can a clinic group recover its share of a rental deposit after moving out of a shared unit?
District Court · 5 November 2026 · [2026] SGDC 367 -
Can an investor get substantial damages for a broken promise to restore a trading account without proving its balance?
District Court · 25 August 2026 · [2026] SGDC 272 -
Does a buyer of a villa never transferred recover the agreed price or only expectation loss?
High Court · 21 July 2026 · [2026] SGHC 153 -
Is an accountant liable for lost interest after failing to place company funds in a fixed deposit?
District Court · 17 July 2026 · [2026] SGDC 232 -
Must a tenant report visible floor damage during a tenancy, or risk losing part of its deposit?
Small Claims Tribunal · 14 July 2026 · [2026] SGSCT 21
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2024] SGHC 179)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer