Tid Plus Design Pte Ltd v Kwek Seng Wee John
[2024] SGHC 187 · HC/OA 381/2024 · cites 17 cases (16 Singapore, 1 foreign) · cited by 1 case
Is a renovation stage complete when the work is done but the waterproofing has failed?
No. The High Court agreed completion needs substantial performance and a major waterproofing defect left the wet works incomplete, and dismissed the contractor's application for leave to appeal.
Step 1: What happened
Tid Plus Design Pte Ltd, an interior design firm, contracted around August 2021 to renovate the house of Mr Kwek Seng Wee John for $82,051.80. Payment was staged: 10% on signing, 40% when works began and 45% on completion of wet works, a stage the parties later agreed would instead fall due on completion of carpentry works. Mr Kwek considered the workmanship substandard, and much of the floor and carpentry work had to be redone or rectified. His family moved in on 18 September 2021, by which time he had paid around $61,400. It was undisputed that defects remained, including leakage from an upstairs toilet. The firm refused to do more work, demanded the unpaid balance of $20,651.80, purported to terminate the contract and sued in the Magistrate's Court. Mr Kwek counterclaimed for rectification costs; all three bathrooms failed independent water ponding tests.
The District Judge held that the failed waterproofing meant the wet works were not substantially complete, so the 45% instalment had not fallen due. He dismissed the firm's claim and awarded $11,957.58 on the counterclaim. After he refused leave to appeal, the firm applied to the High Court in Originating Application No 381 of 2024 for leave to appeal.
Step 2: What the court had to decide
- Whether there was a prima facie case of error in the District Judge's finding that the wet works were not completed
- Whether the decision raised a question of principle or a question of importance warranting leave
- How the court should assess whether a question of general principle or importance arises
Step 3: How the court reasoned
Leave under s 21 of the Supreme Court of Judicature Act 1969 requires a prima facie case of error, a question of general principle decided for the first time, or a question of importance. The court treated the last two as one inquiry, asking whether the law is unsettled, the point difficult, the question general and its answer of wider use; a party's say-so, an adverse result or mere novelty is not enough.
The District Judge's definition of completion focused on the works being ready for use, allowing for minor defects and work still to be done, not on the whole house being habitable. Completion of a stage therefore meant substantial performance of that stage. Any other view would let a contractor declare a stage complete simply to collect payment, and the firm's counsel accepted that some objective element was needed. The waterproofing failure was accepted as a major defect, and wet works with a major defect in one part were not complete. The single joint expert had said only that the works were physically done, even if badly; whether they were contractually complete was for the court. The variation made the instalment payable only after both wet and carpentry works were complete. Any weight on the wider rectification estimate was minor, and moving in for want of alternatives did not mean the bathrooms gave proper sanitation.
The court added that minor defects do not bar progress payments, and an owner who withholds payment over cosmetic flaws risks liability too.
“Just as an unreasonable contractor cannot demand payment for incomplete works (ie, works that are not substantially performed), an unreasonable customer likewise cannot hold the contractor hostage on minor issues that are more sensibly resolved after the renovation is substantially performed or completed.”
[2024] SGHC 187 at [50]
Step 4: The order
The High Court dismissed the application for leave to appeal, finding no error in fact or law and no question of principle or importance. Costs were to be dealt with separately.
Terms in this case
- Permission to appeal
- Approval from a court that some appeals need before they can go ahead, for example where the amount in dispute is small. It is usually given only for an arguable error, a new point of principle or a question of public importance.
- Progress payment
- A payment made in stages during a construction project for work done or goods and services supplied up to that point, rather than one payment at the end. Singapore's security of payment law gives a statutory right to such payments.
- Prima facie case
- Evidence that, if accepted and not answered, would be enough to establish a claim or charge. In a criminal trial, the court calls on the accused to give a defence only if, at the close of the prosecution's evidence, there is some credible evidence on every element of the charge.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Mohamed Faizal |
| What the case was about | Building and Construction Law |
Source: [2024] SGHC 187, High Court, decided — eLitigation. Updated .
Judge
- Mohamed Faizal Delivered the judgment
Parties
- Tid Plus Design Pte Ltd Applicant
- Kwek Seng Wee John Respondent
Counsel
- Axis Law Corporation Firm
- Sim Jin Simm Alina
- Netto & Magin LLC Firm
- Nicholas Leow Zhi Wei
Statutes cited
Cases cited (17)
- Hon G v Tan Pei Li [2023] SGHC 193
- Soo Hoo Khoon Peng v Management Corporation Strata Title Plan No. 2906 [2023] SGHC 355
- Xu Yuanchen v Public Prosecutor [2024] SGCA 17
- [2008] SGHC 199
- [2010] SGHC 302
- [2022] SGHC 313
- [2022] SGHC(A) 16
- [2024] SGMC 22
- [1989] 1 SLR(R) 588
- [1990] 1 SLR(R) 198
- [1997] 2 SLR(R) 862
- [2001] 2 SLR(R) 18
- [2004] 3 SLR(R) 25
- [2011] 3 SLR 859
- [2014] 4 SLR 600
- [2022] 4 SLR 513
- [1972] 1 WLR 1009
Cited by (1)
- Mah Kiat Seng v Suresh Saundrapandian and others [2026] SGDC 243
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Must a homeowner pay a renovation company for variation works priced only after they were done?
Magistrates' Court · 12 June 2026 · [2026] SGMC 71 -
Can a development manager claim a share of cost savings without the board's written approval of its proposals?
High Court · 26 November 2025 · [2025] SGHC 233 -
Can a court reduce an adjudication award for a contractor's fraud that did not affect the award?
High Court (Appellate Division) · 18 September 2024 · [2024] SGHC(A) 28 -
Can an employer recover substantial damages for building defects without proving their extent and resulting loss?
High Court · 27 November 2023 · [2023] SGHC 333 -
Can a contractor pass back charges to a slow subcontractor after the main contractor takes installation work away?
High Court · 31 July 2023 · [2023] SGHC 205 -
Can a court reduce an adjudicated sum because the contractor used false documents to obtain a downpayment?
High Court · 5 July 2023 · [2023] SGHC 186
Referenced in
Statutes interpreted in this judgment
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2024] SGHC 187)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer