Shipworks Engineering Pte Ltd v Sembcorp Marine Integrated Yard Pte Ltd
[2024] SGHC 325 · HC/S 1040/2020 · cites 5 cases (3 Singapore, 2 foreign) · cited by 4 cases
Does a contract's absolute discretion to value work let the paying party value it however it likes?
No. The High Court held even an absolute discretion must be exercised rationally, allowed payment on timesheets with unchallenged signatures but not forged ones, and allowed both the claims and the counterclaim in part.
Step 1: What happened
Shipworks Engineering Pte Ltd and Lanka Marine Services Pte Ltd supplied manpower, sub-task work such as spray-painting and high pressure washing, and miscellaneous services such as toilet cleaning and lorry cranes to Sembcorp Marine Integrated Yard Pte Ltd and Jurong Shipyard Pte Ltd. In Suit No 1040 of 2020, consolidated with three other suits, the plaintiffs claimed $26,048,727.76 under 203 unpaid invoices, after obtaining summary judgment on 114 others, plus $541,152.19 on a quantum meruit for 12 jobs not yet invoiced.
The defendants said the plaintiffs' set of supporting documents had never been received, and that their own records showed irregularities, including reused timesheet serial numbers, forged or copy-pasted signatures of their staff, double claims and inflated quantities. They counterclaimed $20,384,284.41 paid out and $438,235.18 in administrative charges on advance payments. They relied on contract clauses giving them an "absolute" discretion to value the work.
The plaintiffs said they billed on their own timesheets, signed by the defendants' engineers or quality control staff at the worksite, and that partial payments were progress payments for work done.
Step 2: What the court had to decide
- Whether the defendants' contractual discretion to value the works was unfettered or had to be exercised rationally.
- Whether the plaintiffs could be paid on their own timesheets, and what effect forged or fabricated signatures had on their claims.
- Whether the illegality doctrine or the forgeries barred the plaintiffs' claims altogether, including admitted sums.
- Whether the defendants proved the alleged double claims, inflated quantities and unsupported miscellaneous and non-invoiced work, and could recover administrative charges.
Step 3: How the court reasoned
The court held that even a discretion described as absolute must be exercised rationally unless excluded in very clear words, so the defendants could not insist work was undone against the evidence or invent values. The plaintiffs had not shown that their quotations varied the contracts for all work orders, nor that the Unfair Contract Terms Act applied.
The contracts did not prescribe a timesheet format, and the defendants' own records included the plaintiffs' timesheets. A timesheet bearing an unchallenged signature of the defendants' representative was proof of the workers and hours. The defendants' document set had been cobbled together and some originals lost, so photocopies were admissible. Relying on the defendants' handwriting expert, the court found that where signatures were shown to be copy-pasted or not written by the maker, the plaintiffs were responsible, as the defendants had no motive to forge their own staff's signatures; those timesheets could not be paid.
The illegality doctrine did not bar the claims, because the right to payment came from the contracts, and only the evidence was tainted. Nor was the forgery so serious as to corrupt the trial, so the whole claim was not struck out.
The double-claim allegations failed because each invoice had been signed off and reworks could explain repeated work. Downward amendments to work lists stood where based on standard tariff rates, except for one work order where the figures appeared made up. Miscellaneous job documents signed only by the plaintiffs, or unsigned, did not prove the work. The administrative charges agreements clearly entitled the defendants to charge, though only from 27 July 2018.
“The requirement of rationality overrides even “absolute” discretion.”
[2024] SGHC 325 at [17]
Step 4: The order
The High Court partially allowed both the claims and the counterclaim. For each manpower work order the defendants must pay the higher of the sum they admitted or the total of the plaintiffs' timesheets whose signatures were not successfully impugned, with the plaintiffs repaying any overpayment. Claims supported by forged signatures, the 18 unsupported miscellaneous invoices and 11 of the 12 non-invoiced jobs failed. The defendants may recover administrative charges on partial payments from 27 July 2018. The parties were directed to calculate the net figure jointly within four weeks, with costs to be decided later.
Terms in this case
- Illegality
- The doctrine under which a court may refuse to enforce a contract, or to allow a claim, where the contract or its performance involves breaking a statute or is contrary to public policy. Whether money or property already transferred can be recovered depends on further rules.
- Forgery
- Under section 463 of the Penal Code 1871, making a false document or electronic record with intent to cause damage or injury, to support a claim or title, to make a person part with property or enter a contract, or to commit fraud. A civil court may also find a document forged when deciding a dispute, with no charge brought.
- Quantum meruit
- Latin for "as much as he has deserved": a claim for a reasonable sum for work done or services supplied, either under a contract that fixes no price or, where there is no enforceable contract, as a claim in unjust enrichment.
- Counterclaim
- A claim that a defendant brings against the claimant in the same proceedings, rather than starting a separate action. The court can decide the claim and the counterclaim together.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Choo Han Teck |
| What the case was about | Contract |
Source: [2024] SGHC 325, High Court, decided — eLitigation. Updated .
Judge
- Choo Han Teck Delivered the judgment
Parties
- Jurong Shipyard Pte Ltd Defendant
- Lanka Marine Services Pte Ltd Plaintiff
- Sembcorp Marine Integrated Yard Pte Ltd Defendant
- Shipworks Engineering Pte Ltd Plaintiff
Counsel
Statutes cited
Cases cited (5)
- [2022] SGHC 74
- [2013] 3 SLR 666
- [2022] 1 SLR 1318
- [2008] EWHC 1034
- [2023] 1 WLR 2139
Cited by (4)
- Shipworks Engineering Pte Ltd and another v Sembcorp Marine Integrated Yard Pte Ltd and another and another appeal [2026] SGHC(A) 22
- Shipworks Engineering Pte Ltd and another v Sembcorp Marine Integrated Yard Pte Ltd and another [2025] SGHC(A) 19
- JPL Industries Pte Ltd v Lanka Marine Services Pte Ltd [2025] SGHCR 30
- Shipworks Engineering Pte Ltd v Sembcorp Marine Integrated Yard Pte Ltd [2025] SGHC 40
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Does a tutor breach a clause against soliciting students merely by privately teaching a student who left?
Small Claims Tribunal · 12 October 2026 · [2026] SGSCT 27 -
Can a landlord recover both double rent and damages from a tenant who fails to leave?
High Court · 14 November 2025 · [2025] SGHC 226 -
Can a sole shareholder sue a nominee director for losses that are really the company's?
High Court · 4 December 2024 · [2024] SGHC 313 -
Can a company summarily dismiss its chief executive for vulgar emails to staff and confidentiality breaches?
High Court · 14 October 2024 · [2024] SGHC 260 -
Can a purchaser of a food stall business end the contract when the vendor cannot lawfully sublet the stall?
District Court · 13 October 2026 · [2026] SGDC 329 -
Can a claimant enforce an agreement he never communicated with the defendant about?
District Court · 5 October 2026 · [2026] SGDC 328
Referenced in
Statutes interpreted in this judgment
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2024] SGHC 325)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer