Builders Hub Pte Ltd v JP Nelson Equipment Pte Ltd

High Court

[2023] SGHC 120 · HC/OA 738/2022 · cites 14 cases (13 Singapore, 1 foreign)

The question

Does a termination clause alone stop a contractor adjudicating a payment claim served before termination?

The answer

No. The High Court held the clause mattered only if actually engaged, set aside the adjudicator's dismissal and remitted the matter to decide which party validly ended the contract first.

Step 1: What happened

Builders Hub Pte Ltd (BH) was awarded a contract by JP Nelson Equipment Pte Ltd (JP) on or around 8 June 2018 to construct a building. The contract incorporated the REDAS Design and Build Conditions of Contract. On 2 August 2022, JP's Employer's Representative, Infield Projects Pte Ltd, served a notice under cl 30.2.1 stating that the revised completion date was 19 December 2021, that BH was liable for liquidated damages for delay, and that BH had to finish by 30 September 2022 or face termination.

On 18 August 2022 BH served Payment Claim 40 for $2,471,258.29. Each side then accused the other of repudiatory breaches. On 26 August 2022 BH wrote that it accepted JP's alleged repudiation, which BH said was a termination at common law. Later that day JP issued a notice purporting to terminate BH's employment under cl 30.2.2. JP's payment response of 15 September 2022 asserted that BH owed JP $416,503.30.

BH applied for adjudication in SOP/AA 164 of 2022. On 27 October 2022 the adjudicator dismissed the application for want of jurisdiction. He took the view that, where a contract has an express clause on terminating the contractor's employment, a contractor has no right to post-termination payment unless the contract expressly gives one, so the payment claim fell outside the Building and Construction Industry Security of Payment Act 2004 (SOPA). BH applied to the High Court in Originating Application No 738 of 2022 to set aside the determination and have the matter remitted.

Step 2: What the court had to decide

  1. Whether a termination event after Payment Claim 40 was validly served barred BH from seeking adjudication of it
  2. Whether BH was barred because the designated payment certifier had become functus officio
  3. Whether the adjudicator breached the rules of natural justice
  4. Whether waiver, estoppel or s 15(3) of the SOPA stopped JP from raising its jurisdictional objection

Step 3: How the court reasoned

On the first issue, the court disagreed with the adjudicator's default position. The mere presence of a clause on terminating the contractor's employment did nothing unless that clause was actually engaged. Section 5 of the SOPA grants the right to progress payments without general conditions, and s 4(2)(c) excludes a terminated contract only where a suspension-of-payment clause has actually been triggered, which was also the purpose stated in Parliament. Far East Square Pte Ltd v Yau Lee Construction (Singapore) Pte Ltd [2019] 2 SLR 189, Shimizu and Orion-One concerned claims served after the relevant event. Choi Peng Kum, approved in Shimizu, and the general rule that termination does not undo accrued rights supported the opposite view. So the question was whether the contract negated or suspended the accrued right. That depended on who validly terminated first. If JP validly invoked cl 30.2.2, cl 30.3.1 suspended payment until termination costs were ascertained. If BH had already validly terminated that morning, cl 30.3 never applied. The adjudicator had wrongly treated this as immaterial, and the court left the merits of it to him.

On the second issue, the certifier's status did not matter. Under cl 22.4 JP's own payment response took precedence over any interim certificate. BH had served the claim before termination, JP had served its response, BH had not accepted it in writing, and BH then applied within its rights under s 12(2).

On natural justice, the adjudicator's findings were reasonably connected to JP's submission that BH had no contractual entitlement to payment after termination, and both sides had argued s 4(2)(c). There was no unfair surprise.

On waiver and estoppel, Yau Lee held that the duty to raise objections in the payment response does not extend to claims outside the SOPA. Whether cl 30.3 applied was that kind of jurisdictional question. The functus officio point was moot.

From the judgment

“In my view, the mere existence of an employment termination clause in the Contract should not and does not affect a contractor’s entitlement under the contract if it is not engaged on the facts.”

[2023] SGHC 120 at [32]

“Where the suspensory provision in the contract is not invoked or engaged on the facts, s 4(2)(c) does not operate to disentitle a contractor to progress payments.”

[2023] SGHC 120 at [36]

Step 4: The order

The High Court allowed BH's application. Using its powers under ss 27(8)(a) and 27(8)(b) of the SOPA, it set aside the adjudication determination and remitted it to the adjudicator to decide whether cl 30.3 of the REDAS Conditions applied. If it did, the claim fell outside the SOPA and the adjudication application should be dismissed for lack of jurisdiction. If BH had already ended the contract for JP's alleged repudiatory breaches before JP's notice, cl 30.3 was not engaged and the claim should be assessed on its merits. The court rejected BH's natural justice and estoppel arguments and reserved costs for a later hearing.

Terms in this case

Adjudication determination
The decision of an adjudicator on a payment claim under Singapore's security of payment law for the building industry. It must be paid promptly, but the underlying dispute can still be finally decided later in court or arbitration.
Adjudicator
Under Singapore's security of payment law for the building industry, the person appointed to decide a payment dispute quickly between parties to a construction contract, mainly on documents and within short fixed time limits.
Estoppel
A rule that stops a person from going back on a position taken, by words, conduct, an agreed assumption or an earlier judgment, where it would be unjust to allow it, often because another person has relied on that position.
Functus officio
Latin for "having performed one's office": the principle that once a court, tribunal, arbitrator or other body has given its final decision on a matter, or its power to act has lapsed (for example when a statutory time limit runs out), it has no further power to reopen or change it, apart from narrow exceptions such as correcting clerical slips.
Liquidated damages
A sum that a contract fixes in advance as payable if a particular breach occurs, such as a daily rate for late completion. It is enforceable if it is a genuine pre-estimate of the likely loss; a sum that is instead a penalty is not enforceable.
Natural justice
The basic rules of fair procedure that a court, tribunal or other decision-maker must follow: each side must have a fair chance to be heard, and the decision-maker must not be biased or appear to be biased.
Payment claim
A claim for a progress payment that a contractor or supplier serves under Singapore's security of payment law for the building industry. It starts the statutory process, and the other party must answer with a payment response within set time limits.
Progress payment
A payment made in stages during a construction project for work done or goods and services supplied up to that point, rather than one payment at the end. Singapore's security of payment law gives a statutory right to such payments.
Repudiation
Conduct or words by a party to a contract showing that it no longer intends to be bound by the contract. The other party may then choose to end the contract and claim damages.
Security of payment
The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.
Waiver
The giving up of a legal right, such as the right to end a contract for breach. It may happen by choosing between two inconsistent rights (waiver by election) or by a clear representation that a right will not be enforced, relied on by the other party (waiver by estoppel).

Court record

Key facts

Court High Court
Decided
Judge Teh Hwee Hwee
What the case was about Building and Construction Law

Source: [2023] SGHC 120, High Court, decided — eLitigation. Updated .

Judge

Parties

Counsel

Counsel for the claimant
Counsel for the defendant

Statutes cited

Cases cited (14)

SG (1)
  • [2020] SGHC 70
SLR (12)
  • [2007] 4 SLR(R) 364
  • [2007] 4 SLR(R) 413
  • [2008] 1 SLR(R) 663
  • [2009] 4 SLR(R) 602
  • [2011] 4 SLR 477
  • [2013] 4 SLR 972
  • [2014] 1 SLR 1210
  • [2018] 1 SLR 317
  • [2018] 2 SLR 1311
  • [2019] 2 SLR 189
  • [2020] 1 SLR 1338
  • [2021] 1 SLR 791
UK (1)
  • [1962] 2 QB 26

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2023] SGHC 120)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer