Icop Construction (SG) Pte. Ltd. v Tiong Seng Civil Engineering (Private) Limited

High Court (Appellate Division)

[2024] SGHC(A) 1 · AD/CA 100/2022 · cites 19 cases (15 Singapore, 4 foreign)

The question

Can main contractors claim liquidated damages for delay they helped cause when the subcontract has no extension of time clause?

The answer

No. The Appellate Division held that, with no such clause, the main contractor's own acts of prevention made the liquidated damages clause unenforceable, substituted general damages, and allowed the appeal in part.

Step 1: What happened

Tiong Seng Civil Engineering (Private) Limited (TSCE), main contractor on a PUB potable water pipeline project near Henderson Road and River Valley Road, subcontracted the microtunnelling works to ICOP Construction (SG) Pte Ltd in 2017. The works were to be done in four sequential drives using one microtunnel boring machine. The subcontract had no general conditions and no extension of time clause. The project ran well behind schedule. After completing the second drive in early 2019, ICOP terminated the subcontract on 13 March 2019, and TSCE called on ICOP's $570,000 performance bond.

ICOP sued in HC/S 1086/2019, and TSCE counterclaimed. The trial was split. In the first tranche the judge ordered TSCE to pay ICOP $1,333,298.52 and ICOP to pay TSCE $402,790.46 in delay damages. He found ICOP had wrongfully terminated, left the bond question to the second tranche, and stayed payment pending that tranche. ICOP appealed on 13 issues in AD/CA 100/2022. These included the disputed rebuilding of a leaking headwall, alleged defects in a receiving shaft, delays before the planned launch date, rental of the boring machine during TSCE's delay in getting authority approvals, liquidated damages, night-work noise limits, slow pipe jacking and demobilisation, termination, the bond and the stay.

Step 2: What the court had to decide

  1. Whether ICOP was entitled to have the headwall rebuilt and was liable for the resulting delay.
  2. Whether ICOP could recover machine rental for the period of TSCE's delay despite an 18-month minimum lease with a related company.
  3. Whether TSCE could recover liquidated damages when the subcontract had no extension of time clause.
  4. Whether ICOP or TSCE was responsible for the loss of the night-work noise permit.
  5. Whether ICOP validly terminated the subcontract under its termination clause.

Step 3: How the court reasoned

On the headwall, the approved drawing set no requirement that it withstand 1.75 bar of pressure. The figures ICOP relied on described expected face pressure at the cutter head, not a headwall specification. ICOP had no contractual basis to demand reconstruction and bore the delay. The shaft claim failed because the contract required only a 7.5m internal diameter, not working space free of protrusions, and ICOP could not rely on an unpleaded misalignment theory. Delays before the planned launch date were not critical, because the critical task was TSCE's approvals.

On rental, the court treated the cost of an idle machine as a classic standby cost, no different from manpower. The minimum lease with ICOP's related company was irrelevant. Rental was recoverable only from 22 May 2018, when ICOP was actually ready, to 25 June 2018.

On liquidated damages, TSCE conceded that without an extension of time clause, its own acts of prevention made the clause unenforceable and set time at large. General damages were substituted at rates the parties agreed.

On noise, statutory noise limits apply to everyone. TSCE had to obtain a permit, not one free of noise limits, and each party had to control noise from its own equipment. The evidence showed ICOP's generator and slurry plant were major sources and its mitigation was slow, so the permit's loss was ICOP's responsibility. The court preferred TSCE's delay expert's day-by-day analysis.

On termination, the clause required that ICOP had fulfilled its obligations and was prevented from continuing for reasons beyond its control. Neither condition was met: ICOP had caused substantial cascading delays, and it had chosen to keep its machine in Malaysia, showing it did not intend to continue. The bond and stay appeals failed with these findings.

From the judgment

“A breach is not necessarily spent simply because it occurred in the past.”

[2024] SGHC(A) 1 at [280]

Step 4: The order

The Appellate Division allowed the appeal in part. It dismissed ICOP's appeal on most issues, including termination, which remained wrongful, the performance bond and the payment stay. It varied the award for TSCE's delay in obtaining authority approvals to $489,064.89 by agreement, awarded ICOP $255,360 for machine rental, and replaced the liquidated damages against ICOP with general damages of $60,965.16. Costs of the appeal were fixed at $67,000 all in, payable by ICOP to TSCE.

The order in the court's words

Appeal allowed in part

“ICOP succeeded in its appeals on Issues 4 and 5.”

Source: [2024] SGHC(A) 1, High Court (Appellate Division), decided 2 January 2024. Read directly from the judgment.

Terms in this case

Liquidated damages
A sum that a contract fixes in advance as payable if a particular breach occurs, such as a daily rate for late completion. It is enforceable if it is a genuine pre-estimate of the likely loss; a sum that is instead a penalty is not enforceable.
Extension of time
More time, granted by a court or allowed under a contract, to do something after the original deadline, such as filing a document or bringing an appeal, or completing building works.
General damages
Damages for loss that cannot be calculated exactly in money and that the law presumes flows from the wrong, such as pain and suffering in a personal injury claim, or loss of reputation and hurt feelings in defamation; the court assesses a fair sum.
Performance bond
A guarantee, usually from a bank or insurer, given on a contractor's behalf to secure the contractor's performance. If it is payable on demand, the beneficiary can call on it without proving default, and a call is restrained only for fraud or unconscionability.

Court record

Key facts

Court High Court (Appellate Division)
Decided
Judges Kannan Ramesh, Quentin Loh, Woo Bih Li
What the case was about Building and Construction Law, Credit and Security
Outcome Appeal allowed in part

Source: [2024] SGHC(A) 1, High Court (Appellate Division), decided — eLitigation. Updated .

Judges

Parties

  • ICOP Construction (SG) Pte Ltd Appellant
  • Tiong Seng Civil Engineering (Pte) Ltd Respondent

Counsel

Counsel for the respondent
Counsel for the appellant

Statutes cited

Cases cited (19)

SG (5)
  • UBQ v UBR [2023] SGHC(A) 10
  • [2011] SGHC 82
  • [2019] SGHC 4
  • [2022] SGHC 257
  • [2022] SGHC(A) 44
SLR (10)
  • [2003] 2 SLR(R) 170
  • [2004] 3 SLR(R) 288
  • [2006] 3 SLR(R) 769
  • [2007] 4 SLR(R) 413
  • [2009] 4 SLR(R) 602
  • [2013] 4 SLR 193
  • [2015] 5 SLR 1422
  • [2022] 1 SLR 302
  • [2022] 2 SLR 1066
  • [2023] 1 SLR 536
UK (4)
  • [2007] EWHC 305
  • [2008] EWHC 6
  • [2012] EWHC 1773
  • [2016] EWHC 1875

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Referenced in

Statutes interpreted in this judgment

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC(A) 1)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer