DJY v DJZ and another
[2024] SGHC 301 · HC/OA 530/2022 · cites 20 cases (18 Singapore, 2 foreign) · cited by 2 cases
Can a call on a standby letter of credit that secures refunds be restrained as unconscionable?
Not here. The High Court treated the instrument as a performance bond, so unconscionability was available, but found the call strictly complied with its terms and no strong prima facie case of unconscionability, and dismissed the injunction application.
Step 1: What happened
DJY contracted with DJZ on 19 December 2003 to build and assemble an offshore semi-submersible oil and gas production platform for use off the coast of Country X. Later amendments raised the contract price to compensate for the rise of Country X's currency against the US dollar. In 2007 the Federal Audit Court of Country X (FAC) began auditing the contract and ordered payments linked to that rebalancing to be suspended. On 21 November 2007 it allowed DJZ to keep paying DJY on condition that DJY provided a guarantee, and a standby letter of credit was issued in DJZ's favour on 20 February 2008. It was reissued on 28 March 2022 by a bank, the second defendant, for US$126,569,231.12. Payment required, among other things, a copy of the notification receipt of the FAC's final decision declaring the payment null and void, together with a signed statement by DJZ.
On 7 December 2011 the FAC directed DJZ to retain balances, liquidate the guarantees and recover remaining sums. Appeals by DJY, DJZ and another company were dismissed on 27 July 2022, and DJY's motion for clarification was dismissed on 10 August 2022. On 22 August 2022 DJZ called on the standby letter of credit. DJY then brought a series of proceedings in Country X, several of which were dismissed, with some appeals still pending, and began arbitration on 21 December 2023. In Singapore it filed HC/OA 530/2022 on 9 September 2022 for an injunction against DJZ and the bank, and an interim injunction was granted on 14 September 2022. This judgment decided the originating application.
Step 2: What the court had to decide
- Whether the standby letter of credit should be treated as a performance bond or as a letter of credit
- Whether DJZ's call strictly complied with the conditions of the instrument
- Whether DJZ's call was unconscionable or fraudulent so that it ought to be restrained
Step 3: How the court reasoned
On characterisation, the court held that the label was not decisive and the question was whether the instrument was security or a mode of payment. Its purpose, set by the FAC's interim decision, was to secure the refund of payments DJZ made after that decision if the FAC later ruled against them. Its own terms said it was issued to secure that refund. Under the International Standby Practices (ISP98) incorporated into it, the instrument resembled an advance payment standby. The bank's duty to pay arose only on an adverse FAC ruling, a secondary rather than a primary obligation. It was therefore a performance bond.
On strict compliance, the court rejected DJY's reading that the FAC had to declare in express terms that DJZ's payment obligations were invalid. DJY also said the FAC had no power to make such a declaration, which would mean the condition could never be met, and that reading was rejected as unreasonable. Because the words "null and void" were not in quotation marks or blocked text, ISP98 required only a decision with the same meaning. The FAC appeal decision, which the notification receipt linked to and so brought in, found "no legal substantiation" for the payment, and that was enough. On finality, DJZ's expert was preferred. Judicial review in another forum did not make the FAC decision subject to further appeal, and DJY's view would again make the condition impossible to meet.
On unconscionability, the court applied the framework in CEX v CEY and another [2021] 3 SLR 571. DJZ's right to the secured sum had been finally decided by the FAC, separately from any dispute over the contract's validity raised in the later lawsuit and the arbitration. Neither had begun when DJZ called. DJY, which accepted it bore the burden, offered no evidence that DJZ knew it was not entitled. DJZ had waited over ten years after the FAC's first decision before calling, which pointed to restraint. With unconscionability not shown, fraud failed as well.
“In my judgment, the SBLC is linked to the Contract and acts as a security as opposed to a mode of payment by DJY to DJZ.”
[2024] SGHC 301 at [18]
“Here, there was a final determination on DJZ’s entitlement to the sum secured by the SBLC.”
[2024] SGHC 301 at [63]
Step 4: The order
The High Court dismissed DJY's application for an injunction against DJZ and the bank. It accepted that the instrument should be treated as a performance bond, so unconscionability was an available ground. It found, however, that DJZ's call strictly complied with the instrument's conditions and that DJY had not shown a strong prima facie case of unconscionability, and so fraud was not made out either. Costs were left to the parties to agree, failing which written submissions were to be filed.
Terms in this case
- Performance bond
- A guarantee, usually from a bank or insurer, given on a contractor's behalf to secure the contractor's performance. If it is payable on demand, the beneficiary can call on it without proving default, and a call is restrained only for fraud or unconscionability.
- Letter of credit
- A bank's promise, made at a buyer's request, to pay a seller once the seller presents documents that strictly match the terms of the credit. The bank's duty to pay is separate from the sale contract and is refused only in narrow cases such as fraud.
- Unconscionability
- In equity, conduct making it unfair to insist on strict legal rights. A contract or gift obtained by exploiting another's poverty, ignorance or weakness may be set aside unless shown fair and reasonable. A call on an on-demand performance bond or standby credit may be restrained where the call is unconscionable — abusive, unfair or dishonest — a narrower, separate test.
- Interim injunction
- A temporary court order, made before a dispute is finally decided, that stops a party from doing something or requires it to act until trial or further order. It is generally granted where there is a serious question to be tried and the balance of convenience favours it, and the applicant usually undertakes to pay damages if it proves unjustified.
- Prima facie case
- Evidence that, if accepted and not answered, would be enough to establish a claim or charge. In a criminal trial, the court calls on the accused to give a defence only if, at the close of the prosecution's evidence, there is some credible evidence on every element of the charge.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Wong Li Kok, Alex |
| What the case was about | Civil Procedure, Credit and Security |
Source: [2024] SGHC 301, High Court, decided — eLitigation. Updated .
Judge
- Wong Li Kok, Alex Delivered the judgment
Counsel
- WongPartnership LLP Firm
- Foo Hsien Weng
- Jill Ann Koh Ying (Xu Ying)
- Leau Jun Li (Phoebe)
- Lin Weiqi Wendy
- Wee Jong Xuan
Cases cited (20)
- [1994] SGHC 225
- [1992] 2 SLR(R) 20
- [1992] 3 SLR(R) 12
- [1995] 2 SLR(R) 262
- [1997] 1 SLR(R) 277
- [1997] 2 SLR(R) 1020
- [1999] 3 SLR(R) 44
- [2008] 3 SLR(R) 1029
- [2009] 4 SLR(R) 92
- [2011] 2 SLR 47
- [2012] 3 SLR 125
- [2012] 3 SLR 352
- [2016] 3 SLR 557
- [2019] 2 SLR 295
- [2019] 4 SLR 1324
- [2021] 3 SLR 571
- [2024] 1 SLR 1054
- [2024] 1 SLR 287
- [2010] EWCA Civ 582
- [2011] 1 WLR 2900
Cited by (2)
- DJY v DJZ and another [2025] SGHC(A) 18
- DJY v DJZ and another [2025] SGHC 59
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a property owner undo an uncontested possession order over her mortgaged property by alleging an illegal moneylending sham?
High Court · 30 September 2025 · [2025] SGHC 194 -
Can a company in liquidation stop its parent enforcing security while an unfair preference claim is pending?
High Court · 28 November 2024 · [2024] SGHC 302 -
Can a guarantor resist paying by insisting the creditor first use other security for the debt?
High Court · 31 January 2024 · [2024] SGHC 11 -
Can a Singapore court restrain foreign suits that overlap a dispute already proceeding in Singapore?
Singapore International Commercial Court · 12 October 2026 · [2026] SGHC(I) 23 -
Can restrained directors bring a second set-aside application on a ground they held back from the first?
High Court · 25 September 2026 · [2026] SGHC 197 -
Can a district court order a husband to renew his wife's dependant's pass?
District Court · 2 September 2026 · [2026] SGDC 288
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2024] SGHC 301)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer