Hiap Seng Building Construction Pte Ltd v Hock Heng Seng Contractor Pte Ltd

High Court

[2024] SGHC 50 · HC/OA 1176/2023 · cites 6 cases · cited by 1 case

The question

Can a main contractor undo an adjudication by relying on its own early payment response?

The answer

No. The High Court held the early response was invalid but the contractor was estopped by its silence from relying on that, and allowed its application only in part, removing S$157.59 awarded beyond the claim.

Step 1: What happened

Hiap Seng Building Construction Pte Ltd, the main contractor for a residential project, engaged Hock Heng Seng Contractor Pte Ltd as sub-contractor. The sub-contract did not fix dates for payment claims or payment responses. Hock Heng Seng served Payment Claim No. 15 on 5 July 2023. On 27 July 2023 Hiap Seng emailed a progress payment certificate certifying S$15,758.51 before GST and S$16,861.60 with GST. Hock Heng Seng then issued a tax invoice for S$16,861.61, and on 7 August 2023 Hiap Seng sent final accounts confirming the same value of works.

Unpaid, Hock Heng Seng applied for adjudication on 8 September 2023 on the basis that the accepted response amount had not been paid. The adjudicator awarded S$17,019.19, made up of S$15,758.51 plus S$1,260.68 for 8% GST, noting that the payment response had miscalculated the GST. Hiap Seng applied in Originating Application No 1176 of 2023 under s 27 of the SOPA to set aside the determination and the order granting leave to enforce it. It argued that its own payment response was invalid because it was served before the payment claim's deemed service date, so no entitlement to adjudicate arose, and that the adjudicator exceeded his jurisdiction by awarding more than was claimed.

Step 2: What the court had to decide

  1. Whether a payment response served before the deemed service date of the payment claim was valid under s 11(1)(b) of the SOPA.
  2. Whether Hiap Seng was estopped from relying on its own invalid payment response to set aside the determination.
  3. Whether the adjudicator acted ultra vires in awarding more than the amount in the payment response.

Step 3: How the court reasoned

On validity, the payment claim served on 5 July 2023 was deemed served on 31 July 2023, as the parties accepted. Requiring a response within 14 days after the claim is served sets both a start and an end to the period, consistent with the ordinary meaning of within, other SOPA provisions that set only end dates, the Second Reading speech and Asia Grand Pte Ltd v A I Associates Pte Ltd [2023] SGHC 175. Strict timelines serve the SOPA's cashflow purpose, so the 27 July 2023 response was defective. It was nonetheless intended as a payment response, not a draft.

On estoppel, the defect went only to the adjudicator's substantive jurisdiction, not his threshold jurisdiction, so the determination was not void and estoppel could operate; the passages on the response's validity could be severed. Under Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317, silence can be an unequivocal representation where there is a duty to speak. Ordinarily that duty would arise only at the adjudication response, but on these facts it arose once the true deadline for a response passed or the tax invoice was issued. Hiap Seng stayed silent, and Hock Heng Seng lost the chance to apply for adjudication on the basis that no response had been given. Hiap Seng was estopped.

On jurisdiction, Hock Heng Seng had consistently claimed the accepted response amount in its invoice, notice of intention and adjudication application, and never sought to correct it. Applying the fair-notice reasoning in Rong Shun, the adjudicator exceeded his jurisdiction by awarding more, but the excess could be severed. Costs were not awarded because Hock Heng Seng, though substantially successful, had argued issues it could have conceded.

From the judgment

“The early and erroneous submission of the Payment Response was of the applicant’s own doing. The applicant had ample opportunity to raise its objection in a timely way.”

[2024] SGHC 50 at [42]

Step 4: The order

Wong Li Kok, Alex JC allowed the setting aside application in part, reducing the adjudicated amount from S$17,019.19 to S$16,861.60 and ordering the excess of S$157.59 to be released from the payment into court to Hiap Seng. Otherwise the determination stood. No order was made as to costs.

Terms in this case

Security of payment
The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.
Adjudication determination
The decision of an adjudicator on a payment claim under Singapore's security of payment law for the building industry. It must be paid promptly, but the underlying dispute can still be finally decided later in court or arbitration.
Adjudicator
Under Singapore's security of payment law for the building industry, the person appointed to decide a payment dispute quickly between parties to a construction contract, mainly on documents and within short fixed time limits.
Payment claim
A claim for a progress payment that a contractor or supplier serves under Singapore's security of payment law for the building industry. It starts the statutory process, and the other party must answer with a payment response within set time limits.
Progress payment
A payment made in stages during a construction project for work done or goods and services supplied up to that point, rather than one payment at the end. Singapore's security of payment law gives a statutory right to such payments.
Estoppel
A rule that stops a person from going back on a position taken, by words, conduct, an agreed assumption or an earlier judgment, where it would be unjust to allow it, often because another person has relied on that position.
Excess of jurisdiction
Where an arbitral tribunal or other decision-maker decides a matter that falls outside the issues the parties submitted to it, or outside its legal powers. An arbitral award, or the affected part of it, can be set aside on this ground.

Court record

Key facts

Court High Court
Decided
Judge Wong Li Kok, Alex
What the case was about Building and Construction Law, Equity

Source: [2024] SGHC 50, High Court, decided — eLitigation. Updated .

Judge

Parties

  • Hiap Seng Building Construction Pte Ltd Applicant
  • Hock Heng Seng Contractor Pte Ltd Respondent

Counsel

Counsel for the respondent

Statutes cited

Cases cited (6)

SLR (5)
  • [2016] 1 SLR 481
  • [2016] 5 SLR 1011
  • [2017] 4 SLR 359
  • [2018] 1 SLR 317
  • [2019] 2 SLR 189

Cited by (1)

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 50)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer