CGS Construction Pte Ltd v Quek & Quek Civil Engineering Pte Ltd

High Court

[2024] SGHC 183 · HC/OA 438/2024 ( HC/SUM 1388/2024 ) · cites 9 cases (7 Singapore, 2 foreign)

The question

When is a partly oral subcontract a contract in writing under the security of payment law?

The answer

When the terms, or alleged facts, each party relies on in the dispute are in writing, assessed broadly. The High Court found that met and dismissed the application to set aside the adjudication determination.

Step 1: What happened

Quek & Quek Civil Engineering Pte Ltd (Q&Q) was the main contractor for the National Environment Agency (NEA) for the operation and maintenance of landfill equipment, vehicles and a floating platform at Semakau Landfill, and subcontracted the entire works (the SMK3 Works) to CGS Construction Pte Ltd. The works were completed around 28 February 2023. It was not disputed that the work scope was set out in the NEA tender documents, though much of the subcontract was not in writing.

Q&Q's final account of 13 December 2023 valued the subcontract at $12,488,000 and made three deductions: variation omissions, expenses, and a retention sum of $556,145.24. CGS's reply letter, which it relied on as its payment claim, accepted that price for interim purposes but disputed the deductions and claimed $1,949,475.90. In adjudication under the Building and Construction Industry Security of Payment Act 2004 (SOPA), the adjudicator ordered Q&Q to pay $1,633,173.93 (including GST). In SUM 1388/2024 in Originating Application No 438 of 2024, Q&Q applied to set aside the adjudication determination and the related court order.

Step 2: What the court had to decide

  1. Whether there was a contract in writing under s 4 of SOPA, and what it means for the matter in dispute to be in writing under s 4(5).
  2. Whether CGS's reply letter disputing the deductions was a valid payment claim, and whether the adjudicator gave adequate reasons on that point.
  3. Whether the SMK3 Works were construction work within s 3 of SOPA.

Step 3: How the court reasoned

Section 4(5) of SOPA treats a contract not wholly in writing as written if the matter in dispute is in writing. Parliament excluded purely oral contracts because an adjudicator would have no basis to decide what was agreed. Q&Q accepted that the tender documents containing the work scope meant the contract was not purely oral. The court held that a written record of the parties' positions is not enough: any contractual term or agreement a party relies on in the dispute must be in writing, though its construction may be disputed; where a party relies instead on an alleged fact, that fact must be in writing; and the assessment should be broad, bearing in mind SOPA's purpose of supporting contractors' cash flow. Here, the price was recorded in Q&Q's final account and CGS's acceptance of it for interim purposes, Q&Q's variation deduction relied on written tender terms, and the expense deduction relied on an email. The retention deduction rested on no contractual term but on Q&Q's bare factual allegation of damaged equipment, which was recorded in correspondence. Allowing bare assertions to defeat jurisdiction would undermine SOPA.

The test for a valid payment claim in Lee Wee Lick Terence v Chua Say Eng [2013] 1 SLR 401 is whether the formal requirements of s 10(4) and reg 5(2) are met; no additional test of the claimant's objective intention applies, and an overly technical approach is inappropriate. CGS's letter stated the claimed amount, identified the contract, referred to the whole period up to the final account and enclosed a breakdown prepared by Q&Q itself. By reproducing CGS's submissions, the adjudicator showed he had adopted them as his reasons.

Q&Q had not raised the Ministry of Manpower's classification before the adjudicator, so s 27(7) barred it, and in any event that classification and NEA's were not decisive. The scope included building drains, earth bunds and access roads; nothing in s 3(1)(b) excludes ancillary work, and counsel's own description showed the bunds were integral to the landfill. The works were also land reclamation under s 3(1)(d): NEA had likened landfilling to reclamation, and plans for a solar farm on the landfill undercut Q&Q's claim that the site was too toxic for human use.

From the judgment

“The reasoning should demonstrate that the adjudicator had regard to the submissions of the parties and materials before him and that he addressed his mind to the issues raised.”

[2024] SGHC 183 at [64]

Step 4: The order

The High Court dismissed Q&Q's application to set aside the adjudication determination, leaving the adjudicated amount payable. Parties were to file submissions on costs if they could not agree.

Terms in this case

Security of payment
The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.
Adjudication determination
The decision of an adjudicator on a payment claim under Singapore's security of payment law for the building industry. It must be paid promptly, but the underlying dispute can still be finally decided later in court or arbitration.
Adjudicator
Under Singapore's security of payment law for the building industry, the person appointed to decide a payment dispute quickly between parties to a construction contract, mainly on documents and within short fixed time limits.
Payment claim
A claim for a progress payment that a contractor or supplier serves under Singapore's security of payment law for the building industry. It starts the statutory process, and the other party must answer with a payment response within set time limits.

Court record

Key facts

Court High Court
Decided
Judge Kwek Mean Luck
What the case was about Building and Construction Law

Source: [2024] SGHC 183, High Court, decided — eLitigation. Updated .

Judge

Parties

  • CGS Construction Pte Ltd Claimant
  • Quek & Quek Civil Engineering Pte Ltd Respondent

Counsel

Counsel for the respondent
Counsel for the claimant

Statutes cited

Cases cited (9)

SLR (5)
  • [2010] 1 SLR 733
  • [2010] 3 SLR 459
  • [2013] 1 SLR 401
  • [2015] 5 SLR 689
  • [2017] 4 SLR 277
UK (1)
  • [2018] EWHC 314
AU (1)
  • [2017] NSWSC 232

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 183)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer