Full Support Healthcare Limited v Smart Glove International Pte. Ltd.
High Court (Appellate Division)
[2026] SGHC(A) 19 · AD/CA 101/2025 · AD/CA 102/2025 · cites 22 cases (20 Singapore, 2 foreign)
Can a buyer that kept accepting late deliveries without reserving its rights later terminate for those delays?
No, here. The Appellate Division held the buyer had waived by estoppel its rights to terminate and, exceptionally, to damages for the delays, making its cancellation an unjustified renunciation; it dismissed the buyer's appeal and allowed the seller's in part.
Step 1: What happened
During the COVID-19 pandemic, Full Support Healthcare Ltd (FSH), a seller of protective equipment, contracted with Smart Glove International Pte Ltd (SGI) for some two billion gloves. A Supply Agreement of 11 June 2020 was followed by a 1st PO, a 5mil PO and a 2nd PO, under which FSH paid 80% of each tranche in advance. SGI's deliveries were late from the outset, and FSH agreed to each revised schedule. It also accepted six price increases, the price of the 3mil gloves rising from US$82.50 to US$104.20 per 1,000 by April 2021.
When market prices fell, FSH's email of 20 April 2021 cancelled all existing 3mil orders because it could not sell the gloves at the agreed price, and a further email of 6 July 2021 cancelled all open orders and sought a refund. SGI sued in HC/S 49/2022 and FSH counterclaimed. The High Court judge found that SGI repudiated the contract by failing to use all reasonable endeavours to deliver on time, and that FSH could rely on that breach to justify termination on 6 July 2021, though it had itself renounced the contract in the interim. She awarded FSH US$51,239,650.02 for late delivery, ordered refund of US$64,782,300 in advance payments with interest, and gave SGI limited damages. Both parties appealed in AD/CA 101/2025 and AD/CA 102/2025.
Step 2: What the court had to decide
- Whether SGI breached the Supply Agreement through its delays, its price increases and its delay in supplying certificates
- Whether FSH could rely on SGI's unstated repudiatory breach to justify cancelling the orders
- Whether FSH had waived its right to terminate and its right to damages for SGI's delays
- Whether the advance payments were forfeitable deposits and what remedies each party should receive
Step 3: How the court reasoned
The court upheld the finding that SGI repudiated the agreement by overselling its capacity and diverting production. But it held that the price increases were not breaches: the price clause required only that both parties agree that extenuating circumstances warranted a change, and FSH's agreement to each increase was conclusive. Nothing turned on the certificates, which were supplied before termination and caused no proven loss.
The court accepted that the principle in Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte Ltd [2009] 4 SLR(R) 602 could apply even though FSH's emails cited only price and amounted to a renunciation, because it asks whether a right to terminate existed, not what the party intended. The principle was, however, displaced by waiver. From June 2020 to April 2021 FSH accepted every late delivery and revised schedule without reserving its rights, admitted making a commercial decision to continue, and never cited the delays when cancelling. That was an unequivocal representation that it would not terminate for the delays, on which SGI relied by continuing to perform. Actual knowledge is not required for waiver by estoppel, and in any case FSH knew of the delays.
The court held, as an exceptional case, that FSH had also waived its right to damages. By placing new orders in August and November 2020 knowing the delays would likely continue, and without reserving its rights, FSH led SGI to take on more exposure. The no-waiver clause did not help FSH because the waiver rested on positive acts, not mere delay. FSH's cancellation was therefore an unjustified renunciation.
Applying Li Jialin and another v Wingcrown Investment Pte Ltd [2024] 2 SLR 372, the advance payments were not forfeitable: there was no right of forfeiture, the set-off clause pointed the other way, and 80% was not reasonable as an earnest. No interest was due because SGI need not repay until FSH's entitlement was determined. SGI was entitled to the contract price of the produced gloves, since its liability to the manufacturers was an existing one, less mitigation proceeds of US$2,000,414.50. Its storage costs and cancelled-order claims failed for want of proof of loss.
“A wrongful termination or an express renunciation are both, at base, renunciations of the contract albeit couched in different terms.”
[2026] SGHC(A) 19 at [92]
Step 4: The order
The Appellate Division dismissed FSH's appeal and allowed SGI's appeal in part. The award of US$51,239,650 to FSH for late delivery and the pre-judgment interest on the refund were set aside. The advance payments remained refundable, but SGI's damages for produced but undelivered gloves were increased to US$7,644,233.30, leaving a net refund to FSH of US$52,010,681.90 after set-off. FSH was ordered to pay SGI costs of $41,000 and $70,000 for the two appeals and $165,000 for the proceedings below.
Terms in this case
- Waiver
- The giving up of a legal right, such as the right to end a contract for breach. It may happen by choosing between two inconsistent rights (waiver by election) or by a clear representation that a right will not be enforced, relied on by the other party (waiver by estoppel).
- Estoppel
- A rule that stops a person from going back on a position taken, by words, conduct, an agreed assumption or an earlier judgment, where it would be unjust to allow it, often because another person has relied on that position.
- Repudiation
- Conduct or words by a party to a contract showing that it no longer intends to be bound by the contract. The other party may then choose to end the contract and claim damages.
- Breach of contract
- A failure, without lawful excuse, to perform a contractual obligation as and when it is due. Every breach gives the innocent party a right to damages; a sufficiently serious breach may also allow it to end the contract.
- Set-off
- The setting of a sum one party owes another against a sum owed in the other direction, so that only the balance is payable. Its forms include legal set-off between mutual debts, equitable set-off between closely connected claims, and set-off in insolvency, as well as set-off agreed by contract.
- Pre-judgment interest
- Interest a court may add to a sum of money it awards, covering the period before judgment during which the successful party was kept out of the money. Whether to award it, and from when, is for the court to decide.
Court record
Key facts
| Court | High Court (Appellate Division) |
|---|---|
| Decided | |
| Judges | Debbie Ong Siew Ling, See Kee Oon, Steven Chong |
| What the case was about | Contract, Damages |
Source: [2026] SGHC(A) 19, High Court (Appellate Division), decided — eLitigation. Updated .
Judges
- Debbie Ong Siew Ling
- See Kee Oon
- Steven Chong Delivered the judgment
Parties
- Full Support Healthcare Limited Appellant
- Smart Glove International Pte Ltd Respondent
Counsel
Cases cited (22)
- Inter-Pacific Petroleum Pte Ltd v Goh Jin Hian [2024] SGHC 178
- Smart Glove International Pte. Ltd. v Full Support Healthcare Limited [2025] SGHC 168
- [1998] SGHC 87
- [1998] 1 SLR(R) 385
- [2000] 1 SLR(R) 159
- [2006] 3 SLR(R) 374
- [2007] 4 SLR(R) 413
- [2009] 4 SLR(R) 602
- [2012] 1 SLR 152
- [2013] 4 SLR 193
- [2013] 4 SLR 409
- [2014] 2 SLR 905
- [2015] 5 SLR 178
- [2016] 2 SLR 1114
- [2016] 3 SLR 1308
- [2016] 5 SLR 1052
- [2018] 1 SLR 317
- [2018] 4 SLR 882
- [2024] 2 SLR 372
- [2025] 2 SLR 142
- [2024] 2 All ER 747
- [2020] NSWCA 344
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a glove seller keep a buyer's 80% advance payments as deposits after the supply contracts end?
High Court · 22 August 2025 · [2025] SGHC 168 -
Can a borrower avoid repaying a loan by claiming the lender overstated the value of assets sold to him?
High Court · 2 November 2026 · [2026] SGHC 228 -
Can tenants still end a lease for the landlord's breach after paying rent for months knowing of it?
High Court · 23 January 2024 · [2024] SGHC 9 -
Are digital tokens that users could not withdraw from a platform in breach of contract valued at trial?
High Court · 9 February 2026 · [2026] SGHC 31 -
Can a payer refuse to pay on timesheets it calls faint without pleading which ones?
High Court · 13 March 2025 · [2025] SGHC 40 -
Does a charterparty letter of indemnity excuse a carrier delivering cargo without the bills of lading?
High Court · 4 November 2024 · [2024] SGHC 282
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC(A) 19)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer