FULL SUPPORT HEALTHCARE LIMITED v SMART GLOVE INTERNATIONAL PTE. LTD.

[2026] SGHC(A) 19 High Court (Appellate Division) 29 June 2026 • AD/CA 101/2025|AD/CA 102/2025 • 89 min read
22 cases cited (20 SG, 2 foreign)

Key facts

Court High Court (Appellate Division)
Decided
Judges Debbie Ong Siew Ling, See Kee Oon, Steven Chong
Charges / claim Contract, Damages
Counsel Allen & Gledhill LLP, USP Law LLC, Hewage Ushan Saminda Premaratne, Jonathan Tan Ming En, Kwon Ha Jeong, Mak Sushan Melissa, Tan Liqi Joseph, Wong Ling Yun

Source: [2026] SGHC(A) 19, High Court (Appellate Division), decided — eLitigation. Updated .

Catchwords

Practice Areas

Judges (3)

Counsel (8)

Parties (2)

Case Significance

In Full Support Healthcare Ltd v Smart Glove International Pte Ltd and another appeal ([2026] SGHC(A) 19), the Appellate Division of the High Court — Steven Chong JCA, Debbie Ong Siew Ling JAD and See Kee Oon JAD — delivered judgment on 29 June 2026 in cross-appeals Civil Appeal Nos 101 and 102 of 2025, arising from Suit 49 of 2022 between Smart Glove International Pte Ltd and Full Support Healthcare Limited. The judgment, heard on 12 March 2026 and delivered by Steven Chong JCA, concerns contractual breach, waiver, repudiatory discharge, deposits and assessment of damages, and opens by situating the dispute against the COVID-19-era surge in demand for personal protective equipment. The case cites 22 authorities, 20 of them Singapore decisions and 2 foreign.

[2026] SGHC(A) 19 explained

FULL SUPPORT HEALTHCARE LIMITED v SMART GLOVE INTERNATIONAL PTE. LTD. ([2026] SGHC(A) 19) is a Singapore judgment decided by the High Court (Appellate Division) on 29 June 2026. It is categorised under Contract and Damages. It is a recent decision; within this corpus no later judgment has cited it yet. This page summarises what the reported decision covers and links the primary sources — the full judgment, the statutes it cites, and the other cases it engages with — so the decision can be read in context. It is reference information, not legal advice, and it does not state the outcome or any holding beyond what the official judgment records.

What is [2026] SGHC(A) 19 about?

FULL SUPPORT HEALTHCARE LIMITED v SMART GLOVE INTERNATIONAL PTE. LTD. ([2026] SGHC(A) 19) is a High Court (Appellate Division) decision from 2026. Its published catchwords are “Contract — Breach”, “Contract — Waiver”, “Damages — Assessment”, and “Contract — Remedies — Deposits”, which indicate the subject matter the judgment addresses. The full reasoning and orders are in the judgment itself, linked below.

What earlier Singapore cases does [2026] SGHC(A) 19 cite?

Among the in-corpus authorities it refers to are [2025] SGHC 168 and [2024] SGHC 178. The complete list of cases cited, and of later cases that cite this decision, is shown on this page.

Summary

SUPREME COURT OF SINGAPORE
29 June 2026
Case summary
Full Support Healthcare Ltd v Smart Glove International Pte Ltd and another appeal [2026] SGHC(A) 19
Appellate Division of the High Court/Civil Appeals Nos. 101 and 102 of 2025
--------------------------------------------------------------------------------------------------------------------------------------
Decision of the Appellate Division of the High Court (delivered by Justice Steven Chong):
Outcome: The Appellate Division of the High Court (“AD”) dismissed Full Support Healthcare Limited’s (“FSH”) appeal in AD/CA 101/2025 and allowed Smart Glove International Pte Ltd’s (“SGI”) appeal in AD/CA 102/2025 in part. The AD found that FSH had waived both its right to terminate the Supply Agreement and the 1st Purchase Order (“PO”) and 2nd PO (collectively, the “3mil POs”) and its right to claim damages for SGI’s repudiatory breach of cl 1.2 of the Supply Agreement. FSH was found to have itself committed a repudiatory breach of the Supply Agreement and the 3mil POs by renouncing the Supply Agreement and the 3mil POs. The AD also found that SGI was not in breach of cl 2.1 of the Supply Agreement, reversing the decision of the court below. The AD therefore revised the damages payable in relation to SGI’s claim for the price and storage costs of the 3mil gloves which it had already produced under the 3mil POs, but which had not been delivered (“Produced Gloves Claim”), from US$282,560.60 to US$7,644,233.30. The net sum of US$52,010,681.90 was ordered to be paid to FSH, representing the refundable advance payments of US$64,782,300 less the sums due to SGI under the unpaid invoices (“Unpaid Invoices Claim”) (US$5,127,384.80) and the Produced Gloves Claim (US$7,644,233.30).
Pertinent and significant points of the judgment:
•  The principle in Alliance Concrete Singapore Pte Ltd v Comfort Resources Pte Ltd [2009] 4 SLR(R) 602 (Comfort Resources), that a contracting party who gives a wrong reason for termination does not thereby deprive himself of a justification that in fact existed at the time, applies even where that party’s manifested intention was to renounce the contract rather than to terminate it. However, the principle remains subject to certain qualifications, including whether there was waiver by election and/or waiver by estoppel.
•  A party may waive not only its right to terminate a contract but also its right to claim damages for a repudiatory breach by estoppel, where its conduct constitutes a clear and unequivocal representation that it will forbear from enforcing those rights, and the other party relies on that representation to its detriment. Although it will be a rare case for a party to be taken to have waived a right to claim damages, the exceptional facts of this case supported such an inference.
•  The proper measure of damages for a seller’s claim arising from a buyer’s failure to take delivery of goods is the full contractual price, not merely the seller’s net profit margin, even where the seller has not yet paid its own suppliers for the goods. This is because an unpaid liability to a supplier is itself capable of constituting recoverable loss.
1 AD/CA 101/2025 (“AD 101”) and AD/CA 102/2025 (“AD 102”) were cross-appeals against the decision of a judge in the General Division of the High Court of Singapore (“Judge”) regarding alleged breaches of the Supply Agreement and the 3mil POs. AD 101 concerned FSH’s appeal against the Judge’s finding that FSH had breached the Agreements by refusing to accept delivery of gloves before it terminated the Supply Agreement and the 3mil POs. AD 102 in turn concerned SGI’s appeal against, amongst other things, the Judge’s finding that FSH had validly terminated the Supply Agreement and the 3mil POs.
Background to the appeal and material facts
2 In June 2020, at the height of the COVID-19 pandemic, FSH engaged SGI to produce and supply gloves for on-selling. The parties entered into four agreements: the Supply Agreement, the 1st PO which was issued in June 2020, a PO for 5mil gloves which was issued in August 2020 (“the 5mil PO”), and the 2nd PO which was issued in November 2020 (collectively, the “Agreements”). The Supply Agreement was the master agreement governing all three POs. Under the Agreements, SGI was to supply approximately two billion gloves to FSH in accordance with agreed delivery schedules. FSH was required to make advance payments of 80% of the purchase price for each tranche of orders, with the remaining 20% payable before or upon shipment.
3 From the outset in June 2020, SGI failed to adhere to the agreed delivery schedules. Despite persistent and significant delays, FSH repeatedly accepted revised delivery schedules proposed by SGI, continued to place new orders (including the 5mil PO in August 2020 and the 2nd PO in November 2020), and accepted multiple price increases under the 3mil POs between October 2020 and April 2021, with the price rising from the original US$82.50 per 1,000 gloves to US$104.20 per 1,000 gloves. At no point during this period did FSH allege any breach by SGI or reserve its rights.
4 By early 2021, the market price of gloves had dropped sharply and cheaper alternative suppliers had emerged. On 20 April 2021, FSH sent an email to SGI purporting to cancel all existing 3mil orders, citing the commercially unviable price rather than any breach by SGI (“20 April 2021 E-mail”). FSH then ceased taking delivery of 3mil gloves under the 3mil POs. Negotiations over pricing failed, and on 6 July 2021, FSH sent a further email cancelling all open purchase orders and demanding a refund of the advance payments (“6 July 2021 E-mail”).
5 SGI commenced HC/S 49/2022 against FSH, alleging wrongful repudiation of the Supply Agreement and the 3mil POs. FSH counterclaimed, alleging that SGI had committed repudiatory breaches entitling FSH to terminate the Agreements.
6 The Judge found that SGI had committed repudiatory breaches of the Supply Agreement, which entitled FSH to terminate the Supply Agreement and the 3mil POs. However, the Judge found that FSH only terminated the Supply Agreement and the 3mil POs through the 6 July 2021 E-mail and not the 20 April 2021 E-mail. Therefore, the Judge found that FSH was also in breach from 20 April 2021 to 6 July 2021.
7 As a result of FSH’s breach, the Judge awarded SGI only US$282,560.60 in damages for the gloves which were produced but not shipped to FSH. This sum accounted for the loss of profits that SGI would have made (ie, 5% of the applicable price).
8 As a result of SGI’s breach, the Judge awarded FSH US$51,239,650 in damages for the late deliveries. Also, the Judge found that the advance payments were refundable and not in the nature of forfeitable deposits. Therefore, the Judge found that FSH was entitled to recover the refundable advance payments in unjust enrichment. Pre-judgment interest of 5.33% per annum from 6 July 2021 was awarded on US$59,654,915.20, which was the advance payments less the sum outstanding under certain unpaid invoices (amounting to US$5,127,384.80) which FSH accepted should be set off.
9 Both FSH and SGI appealed against the Judge’s decision in AD 101 and AD 102, respectively.
Decision on appeal
Issue 1: Whether SGI had breached the Supply Agreement
10 The AD affirmed the Judge’s finding that SGI had committed a repudiatory breach of cl 1.2 of the Supply Agreement by failing to use all reasonable endeavours to meet the agreed delivery schedules. SGI had oversold its production capacity and diverted capacity to fulfil orders from other customers, thereby depriving FSH of substantially the whole benefit of the time-sensitive Agreements. This constituted a Situation 3B repudiatory breach under the RDC Concrete Pte Ltd v Sato Kogyo (S) Pte Ltd and another appeal [2007] 4 SLR(R) 413 (“RDC Concrete”) framework: at [56].
11 However, the AD disagreed with the Judge’s finding that SGI had breached cl 2.1 by increasing the prices of the gloves. The court held that cl 2.1 contained a single composite requirement (ie, that there were extenuating circumstances beyond SGI’s control that both parties agreed warranted a price change), rather than two separate cumulative requirements. FSH’s agreement to the price increases was, therefore, conclusive of the matter. By agreeing to each price increase, FSH had necessarily accepted that the extenuating circumstances cited by SGI on each occasion were valid. The price increases were thus effected in accordance with cl 2.1 and there could not have been any breach by SGI on this front: at [65]–[71].
12 The AD also found that as nothing turned on SGI’s alleged breach of cl 3.2, it was unnecessary for the Judge to have resorted to equitable rectification of the Supply Agreement to impose an obligation on SGI to furnish the EN455 certificates within a few days of FSH’s request: at [74]–[75].
Issue 2: Whether FSH had terminated the Supply Agreement
13 The AD found that the principle in Comfort Resources would apply in the situation presented by the present case where there was a disconnect between FSH’s manifested intention (ie, to commit a repudiatory breach) and the intention that was sought to be retrospectively imputed to FSH (ie, to accept a repudiatory breach by SGI). This was because the principle in Comfort Resources is not focused on what the intention of the party seeking to terminate was at the time, but whether he had a right of termination. As a matter of law, the effect of a contracting party having wrongfully terminated the contract and expressly renouncing the contract is the same: at [92]–[93].
14 However, on the facts of this case, the AD found that FSH had waived its right to terminate the Supply Agreement and the 3mil POs by estoppel. Throughout the contractual relationship from June 2020 to April 2021, FSH accepted every delayed delivery without reservation, agreed to each revised delivery schedule, and placed two further purchase orders despite being fully aware of SGI’s persistent and severe delays. This constituted a clear and unequivocal representation that it would forbear from exercising its right to terminate, on which SGI relied to its detriment. The AD rejected the Judge’s findings that FSH lacked knowledge of SGI’s breach of cl 1.2 at the material time and that any waiver was only temporary, noting that FSH’s failure to cite the delays as a ground for termination even when it ultimately sought to end the relationship made it clear that it had decided to waive that right entirely: at [107]–[134].
15 Because FSH had waived its right to terminate, FSH was not entitled to cancel the open orders under the Supply Agreement and the 3mil POs. Thus, FSH was in breach of the Supply Agreement and the 3mil POs in refusing to take deliveries of the gloves: at [157].
Issue 3: The remedies
16 The AD found that FSH had waived its right to claim damages for SGI’s breach of cl 1.2 by estoppel. Although the court acknowledged that waiver of a right to claim damages would be rare in a commercial context, the exceptional facts of this case supported such an inference. FSH’s conduct in placing the 5mil PO and the 2nd PO despite full knowledge of SGI’s persistent delays and without any reservation of rights constituted an unequivocal representation that it would not seek damages for those delays, on which SGI relied to its detriment by accepting further orders and thereby exposing itself to additional liability. It would have been inequitable to allow FSH to retain the benefit of SGI’s acceptance of new orders while simultaneously pursuing damages for the very delays it had accepted without complaint. Thus, the Judge’s award of damages arising from the breach was set aside: at [139]–[150], and [160].
17 The AD upheld the Judge’s finding that the 80% advance payments totalling US$64,782,300 were refundable advance payments and not forfeitable deposits, applying the framework in Li Jialin and another v Wingcrown Investment Pte Ltd [2024] 2 SLR 372. There was no express right to forfeit the payments. Nor could such a right be implied into the Supply Agreement as cl 2.4 of the Supply Agreement, which provided for set-off of advance payments against outstanding invoices, was inconsistent with a right of forfeiture. In any event, an advance payment of 80% of the total contract price was not reasonable as an earnest and could not constitute a true deposit, both in terms of its percentage of the total price and its absolute quantum. Instead, SGI was required to return the sums to FSH on the ground of unjust enrichment for a total failure of consideration: at [163]–[170].
18 The AD set aside the Judge’s decision on awarding pre-judgment interest on the refundable advance payments. The basis of the award for pre-judgment interest lies in the fact that the unsuccessful party had wrongfully kept the successful party out of monies to which he had shown to be entitled, during which time, the unsuccessful party instead had the use of it. Here, because the AD found that FSH had waived its right to terminate, SGI was vested with the choice to terminate the Supply Agreement and the 3mil POs for FSH’s subsequent breach in refusing to take delivery of the gloves. SGI had, in fact, elected to affirm the Supply Agreement and the 3mil POs. Therefore, SGI was under no obligation to return the refundable advance payments to FSH until FSH’s entitlement to them was finally determined by the court. Thus, the award of pre-judgment interest was set aside: at [172]–[175].
19 The only dispute regarding the Unpaid Invoices Claim was whether pre-judgment interest ought to be awarded for the sum. The AD agreed with the Judge that no interest should be ordered as SGI could have set off the advance payments it had received from FSH against the outstanding invoices due under the 3mil POs and the 5mil PO: at [176]–[178].
20 The AD increased SGI’s damages under the Produced Gloves Claim from US$282,560.60 to US$7,644,233.30. This was because the proper measure of damages for the 92,559,000 gloves which were produced but not delivered was the full contractual price of the gloves, not merely SGI’s net profit margin. While there was no evidence that SGI had yet to pay any costs to its suppliers (“SGG Manufacturers”), the fact remained that SGI was strictly liable to pay the SGG Manufacturers for the gloves they had produced. This unpaid liability in itself constituted recoverable loss. The decision in Freight Connect (S) Pte Ltd v Paragon Shipping Pte Ltd [2015] 5 SLR 178 was not applicable to the present case, as it concerned potential future third-party damages claims whereas SGI’s liability to the SGG Manufacturers had already crystallised: at [180]–[186] and [191].
21 The AD affirmed the Judge’s finding that SGI had failed to prove any loss arising from FSH’s cancellation of the open orders under the 3mil POs. SGI had fully mitigated its losses by reallocating its production capacity to fulfilling new orders from other customers, and had not proven that it earned lesser profits under those new orders as compared to the cancelled orders with FSH: at [194]–[195].
This summary is provided to assist in the understanding of the Court’s grounds of decision. It is not intended to be a substitute for the reasons of the Court. All numbers in bold font and square brackets refer to the corresponding paragraph numbers in the Court’s grounds of decision.

Who heard the appeal in Full Support Healthcare v Smart Glove International ([2026] SGHC(A) 19), and what contract issues were at stake?

Steven Chong JCA, Debbie Ong Siew Ling JAD and See Kee Oon JAD decided the cross-appeals (Civil Appeals 101 and 102 of 2025) on 29 June 2026, addressing repudiatory breach, waiver, deposits and assessment of damages arising from a PPE supply dispute originating in Suit 49 of 2022.

Cases Cited (22)

SLR (17)
[1998] 1 SLR(R) 385 [2000] 1 SLR(R) 159 [2006] 3 SLR(R) 374 [2007] 4 SLR(R) 413 [2009] 4 SLR(R) 602 [2012] 1 SLR 152 [2013] 4 SLR 193 [2013] 4 SLR 409 [2014] 2 SLR 905 [2015] 5 SLR 178 [2016] 2 SLR 1114 [2016] 3 SLR 1308 [2016] 5 SLR 1052 [2018] 1 SLR 317 [2018] 4 SLR 882 [2024] 2 SLR 372 [2025] 2 SLR 142
UK (1)
[2024] 2 All ER 747
AU (1)
[2020] NSWCA 344

Related cases

Other Singapore judgments involving the same parties or counsel.

Judgment

Read the full judgment on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2026] SGHC(A) 19)