JKN v JKO
[2026] SGSCT 23 · SCT/15139/2026 · cites 5 cases (4 Singapore, 1 foreign)
Is a renovation company bound by a contract signed only by its freelance interior designer?
Yes, here. The designer had actual and apparent authority, and the company acted on the contract; its refusal to continue was a repudiatory breach, so the tribunal allowed the claim, awarding damages capped at $20,000 and $275 disbursements.
Step 1: What happened
The claimant, JKO, owned a five-room HDB flat. On 27 July 2025 he engaged the respondent, JKN, an interior design company whose sole director and shareholder represented it in the proceedings, to renovate the flat for $70,800. The contract was prepared and signed for the company by one of its freelance interior designers. By 24 September 2025 the claimant had paid $42,480, being 60% of the contract value, and work began two days later.
On 9 November 2025 the director came to believe that the designer had allegedly committed the company to an unprofitable deal and siphoned off money meant for subcontractors, leaving it, by the director's account, about $32,000 out of pocket. After a meeting, the company issued a revised quotation of $86,266.50, an increase of $15,466.50. When the claimant refused it, the director told him on 13 November 2025 that the company would not complete the electrical works promised free of charge and would enter the flat to remove those already installed, would not lay the vinyl flooring, and would put the renovation on hold. The claimant changed the lock to the gate that day.
The unfinished works were valued at $21,450, and the claimant paid another company $39,558 to complete them. He brought Small Claims Tribunals Claim No 15139 of 2026, limiting his claim to $20,000 to stay within the tribunal's jurisdiction. The company said it was not bound by a contract its director had not signed or chopped, and that the claimant breached it by locking out its workers.
Step 2: What the court had to decide
- Whether the respondent company was bound by a contract signed only by its freelance interior designer
- Whether the respondent or the claimant repudiated the contract
- Whether the respondent could unilaterally raise the contract price through its revised quotation
- Whether damages should be measured as a refund of the unfinished works or as the cost of cure
Step 3: How the court reasoned
The tribunal found the company bound by the contract and called its disavowal a flimsy afterthought. The director admitted that the designer secured deals for the company and was paid commission for this one, that the company engaged and paid the subcontractors, that it received the $42,480, and he personally signed the HDB indemnity form for the hacking works. The company had adopted and acted on the contract, and its own argument that the claimant breached it assumed the contract existed. The designer had actual authority, and in any case apparent authority, and the indoor management rule allowed a good-faith customer to assume internal formalities had been met. The designer's alleged misdeeds, even at their highest, were a matter between the company and him.
The company's three positions on 13 November 2025 together amounted to a refusal to carry on, which was a repudiatory breach. The claimant accepted it by changing the lock, which he did only after the threat to enter and strip out installed fixtures that were now his property.
The revised quotation was at most an offer to vary the contract, and a variation needs acceptance and consideration (Aero-Gate Pte Ltd v Engen Marine Engineering Pte Ltd [2013] 4 SLR 409). The director could not show the increase reflected changes in scope.
On damages, the tribunal held that the correct measure for a construction contract is the cost of cure, not a refund of the price paid. That cost was $39,558, the respondent raised no failure to mitigate, and the claim was capped at $20,000.
“To put it plainly, they were not the Claimant’s problem, and they did not relieve the Respondent of its obligations under the Contract.”
[2026] SGSCT 23 at [20]
“A refund and the cost of cure are different measures, and they may not always yield the same figure.”
[2026] SGSCT 23 at [36]
Step 4: The order
The tribunal allowed the claim in full. It ordered the respondent to pay the claimant $20,275, made up of $20,000 in damages and $275 in disbursements for the filing fee and translation of audio recordings. No order was made as to costs.
The order in the court's words
Claim allowed“For the foregoing reasons, I ordered the Respondent to pay the Claimant $20,275, which consisted of $20,000 plus $275 for disbursements, by 3 September 2026.”
Source: [2026] SGSCT 23, Small Claims Tribunal, decided 17 September 2026. Read directly from the judgment.
Terms in this case
- Actual authority
- The authority a principal has really given an agent, either in express words or implied from the agent's role or the dealings between them. Acts within it bind the principal.
- Apparent authority
- Authority that an agent appears to have because the principal led an outsider to believe the agent could act for it. The principal is bound by the agent's act even though it never actually gave that authority.
- Repudiation
- Conduct or words by a party to a contract showing that it no longer intends to be bound by the contract. The other party may then choose to end the contract and claim damages.
- Breach of contract
- A failure, without lawful excuse, to perform a contractual obligation as and when it is due. Every breach gives the innocent party a right to damages; a sufficiently serious breach may also allow it to end the contract.
Court record
Key facts
| Court | Small Claims Tribunal |
|---|---|
| Decided | |
| Judge | Leon Abraham Tan |
| What the case was about | Contract, Agency, Companies |
| Outcome | Claim allowed |
Source: [2026] SGSCT 23, Small Claims Tribunal, decided — eLitigation. Updated .
Judge
- Leon Abraham Tan Delivered the judgment
Parties
- JKN Respondent
- JKO Claimant
Statutes cited
Cases cited (5)
- [2015] SGHC 190
- [2000] 2 SLR(R) 407
- [2010] 2 SLR 1154
- [2013] 4 SLR 409
- [1986] AC 717
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a business renting a printer avoid payment by claiming the machine was oversold before signing?
High Court · 26 October 2026 · [2026] SGHC 225 -
Can an investor get substantial damages for a broken promise to restore a trading account without proving its balance?
District Court · 25 August 2026 · [2026] SGDC 272 -
Can a furniture supplier withhold shipping a batch the contractor has not fully paid for?
High Court · 10 April 2025 · [2025] SGHC 64 -
Can a lender to a joint-venture company sue its fellow founding shareholders on an implied promise of repayment?
High Court · 9 April 2025 · [2025] SGHC 63 -
Does a charterparty letter of indemnity excuse a carrier delivering cargo without the bills of lading?
High Court · 4 November 2024 · [2024] SGHC 282 -
Can investors get specific performance of a watch company's promise to buy back their watches?
High Court · 30 April 2024 · [2024] SGHC 110
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGSCT 23)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer