Star Engineering Pte Ltd v Pollisum Engineering Pte Ltd and another

Court of Appeal

[2024] SGCA 30 · CA/CA 9/2024 · cites 10 cases

The question

Was there a real risk of inconsistent findings that barred staying a performance bond dispute for arbitration?

The answer

No. The Court of Appeal held that, the employer having in effect treated the on-demand bond as conditional, no live dispute involved the issuer and its entitlement fell within the arbitration clause; it dismissed the contractor's appeal.

Step 1: What happened

Pollisum Engineering Pte Ltd engaged Star Engineering Pte Ltd around 25 September 2019 to design, build and maintain a construction project on the REDAS Design and Build Conditions as varied by Particular Conditions. Star Engineering provided an unconditional on-demand performance bond for $856,000 issued by Great Eastern General Insurance Limited. The bond gave non-exclusive jurisdiction to the Singapore courts, while the contract had a wide arbitration clause, and the Particular Conditions sent any dispute the contractor had about a call on the bond to arbitration. They also barred the contractor from restraining a call except for fraud.

Pollisum Engineering terminated the contract on 28 March 2023 and on 30 October 2023 demanded payment under the bond, alleging defects and a late Temporary Occupation Permit. Star Engineering's essential contention was that the demand was fraudulent. It filed HC/OA 1135/2023 to restrain payment and obtained a temporary restraining order without notice. Pollisum Engineering did not try to set that order aside but applied to stay the action in favour of arbitration. An assistant registrar refused the stay; the High Court allowed Pollisum Engineering's appeal, staying the claim against it in favour of arbitration and granting a case management stay as to Great Eastern. Star Engineering appealed in Civil Appeal No 9 of 2024.

Step 2: What the court had to decide

  1. Whether the court proceedings over the bond demand should be stayed in favour of arbitration
  2. Whether the risk of inconsistent findings between court and tribunal was a sufficient reason to refuse a stay
  3. How the law on interfering with payment under an on-demand performance bond bore on the parties' positions

Step 3: How the court reasoned

The court held that the matter had become needlessly tangled through errors on both sides. An on-demand bond is meant to be as good as cash, and the issuer is not concerned with the underlying dispute. Payment can be restrained only on a strong prima facie case of fraud or, where not excluded, unconscionability; here the contract excluded unconscionability. Properly read, the clauses meant any interference with payment had to be sought from the court on the ground of fraud, while disputes over how much Pollisum Engineering was finally entitled to keep would go to arbitration, with any over-payment refunded.

Pollisum Engineering should therefore have moved to set aside the restraining order unless it accepted there was strong evidence of fraud. Instead, in the court's view, by seeking a stay so that its entitlement could be decided in arbitration, it had in effect treated the bond as conditional, and it was too late to change course. It had added to the confusion by saying on appeal that Star Engineering should start the arbitration.

Star Engineering's appeal was described as wholly illogical and baseless. With the bond now in effect treated as conditional, there was no live dispute involving Great Eastern and no real risk of inconsistent findings: the arbitration outcome would decide whether any payment was due. Pollisum Engineering's ultimate entitlement plainly fell within the arbitration clause. As to who should begin the arbitration, either party had every reason to do so.

From the judgment

“Turning finally to the seeming impasse as to who should commence the arbitration, this again is a needless tempest in a teacup.”

[2024] SGCA 30 at [44]

Step 4: The order

The Court of Appeal dismissed the appeal, leaving the stay in favour of arbitration and the case management stay in place. It said it would hear the parties on costs, observing that much time and cost seemed to it to have been wasted by ill-advised positions on both sides.

The order in the court's words

Appeal dismissed

“…we therefore dismiss the appeal.”

Source: [2024] SGCA 30, Court of Appeal, decided 19 August 2024. Read directly from the judgment.

Terms in this case

Performance bond
A guarantee, usually from a bank or insurer, given on a contractor's behalf to secure the contractor's performance. If it is payable on demand, the beneficiary can call on it without proving default, and a call is restrained only for fraud or unconscionability.
Arbitration agreement
An agreement, usually a clause in a contract, by which the parties agree to send their disputes to arbitration instead of to the courts. A court will generally stay court proceedings brought in breach of it.

Court record

Key facts

Court Court of Appeal
Decided
Judges Steven Chong, Sundaresh Menon
What the case was about Arbitration
Outcome Appeal dismissed

Source: [2024] SGCA 30, Court of Appeal, decided — eLitigation. Updated .

Judges

Parties

  • Great Eastern General Insurance Limited Respondent
  • Pollisum Engineering Pte Ltd Respondent
  • Star Engineering Pte Ltd Appellant

Counsel

Counsel for the appellant
Counsel for the respondent

Statutes cited

Cases cited (10)

SLR (10)
  • [1990] 2 SLR(R) 520
  • [1995] 2 SLR(R) 262
  • [1999] 3 SLR(R) 44
  • [2010] 2 SLR 329
  • [2012] 3 SLR 125
  • [2012] 3 SLR 352
  • [2016] 3 SLR 557
  • [2019] 2 SLR 295
  • [2023] 2 SLR 389
  • [2024] 3 SLR 1031

Related cases

Other Singapore judgments on the same subject, most closely matched first.

  • Must a court finally decide whether a fund is bound by an arbitration clause before staying its insolvency applications?

    Singapore International Commercial Court · 17 September 2026 · [2026] SGHC(I) 19
  • Can a company avoid winding up by invoking arbitration over a debt a third party assigned to the creditor?

    High Court · 22 January 2026 · [2026] SGHC 18
  • Must a court stay a solicitor's bill assessment because the client says the engagement is void?

    Court of Appeal · 11 June 2025 · [2025] SGCA 25
  • Will a court extend a deadline to start the arbitration on which a stay depends?

    Singapore International Commercial Court · 2 May 2025 · [2025] SGHC(I) 14
  • Can a claimant ask the court to stay its own action in favour of arbitration?

    High Court Registrar · 24 April 2025 · [2025] SGHCR 7
  • Can a court stay enforcement of an arbitral award for arbitration under a later settlement deed?

    Singapore International Commercial Court · 16 April 2025 · [2025] SGHC(I) 11

Referenced in

Statutes interpreted in this judgment

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGCA 30)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer