DBX and another v DBZ
Singapore International Commercial Court
[2024] SGHC(I) 5 · SIC/OA 10/2023 · cites 6 cases · cited by 3 cases
Can costs incurred before a case moves to the commercial court exceed the scaled guideline range?
Yes, moderately. The court scaled the guideline range to the pre-transfer stage, allowed a moderate uplift for the considerable volume of materials, fixed those costs at $22,000, and ordered costs of $144,000 in total.
Step 1: What happened
In DBX and another v DBZ [2023] SGHC(I) 18, given on 15 November 2023, the Singapore International Commercial Court dismissed the applicants' application in Originating Application No 10 of 2023 to set aside two arbitral awards and ordered them to pay the respondent's costs. The parties could not agree the amount. The case had been transferred to the SICC; the Deputy Registrar directed that costs incurred before the transfer be assessed under O 21 of the Rules of Court 2021 and the Costs Guidelines in Appendix G, and costs after the transfer under O 22 of the SICC Rules 2021.
The respondent claimed $65,000 for pre-transfer costs, $115,000 for post-transfer costs and $7,000 for preparing costs submissions, together with disbursements of $7,709.38 and HKD151,978.26 for its Hong Kong law expert. The applicants proposed $16,288 and $45,000 respectively and did not dispute the other items.
Step 2: What the court had to decide
- What amount of pre-transfer costs was reasonable under O 21 of the Rules of Court 2021 and the Costs Guidelines, including whether an uplift was justified.
- Whether the post-transfer costs claimed were proportionate and reasonable under the SICC's subjective approach in O 22 of the SICC Rules.
Step 3: How the court reasoned
Pre-transfer costs are assessed objectively, as explained in Senda International Capital Ltd v Kiri Industries Ltd [2023] 1 SLR 96, guided by the Costs Guidelines and precedents, with room for an uplift where the circumstances warrant. The guideline range of $13,000 to $40,000 is for a whole arbitration application, so it had to be scaled to the pre-transfer stage using the ratio of pre- to post-transfer costs, giving a starting range of $5,293.60 to $16,288. The respondent's $65,000 was a considerable departure that its submissions masked, and was not supported by the cases it cited. The applicants' approach of applying a fixed percentage of actual costs drawn from two cases was also unsound, as those percentages depend on each case's circumstances. Starting near the top of the range, the court found the extra complexity from two awards, foreign law and the novel point on corrections mattered mostly to the hearing rather than the pre-transfer work. However, the large volume of material warranted a moderate uplift, and the applicants' conduct had not gone beyond ordinary litigation.
Post-transfer costs are assessed subjectively: the starting point is the costs actually incurred, tested for proportionality and reasonableness, and once these are evidenced the paying party must show they are unreasonable. The applicants made no real attempt to do so. Simply pointing to the $45,000 awarded in CJM and others v CJT [2021] 5 SLR 222, where that was all the defendant sought, was at odds with the subjective approach. The respondent's claim, already reduced from its actual costs of $125,940, was not shown to be disproportionate or unreasonable, and the research on the effect of the corrections had been helpful.
“Having regard to all the Respondent’s submissions, abandonment of the Costs Guidelines is not warranted, but a moderate uplift is.”
[2024] SGHC(I) 5 at [13]
Step 4: The order
The court fixed the respondent's pre-transfer costs at $22,000 and allowed post-transfer costs of $115,000, so that the applicants were ordered to pay costs of $144,000 in total, plus disbursements of $7,709.38 and HKD151,978.26.
Court record
Key facts
| Court | Singapore International Commercial Court |
|---|---|
| Decided | |
| Judge | Roger Giles |
| What the case was about | Arbitration |
Source: [2024] SGHC(I) 5, Singapore International Commercial Court, decided — eLitigation. Updated .
Judge
- Roger Giles Delivered the judgment
Parties
- DBX Applicant
- DBY Applicant
- DBZ Respondent
Counsel
Cases cited (6)
- DBX and another v DBZ [2023] SGHC(I) 18
- [2021] 5 SLR 222
- [2022] 1 SLR 88
- [2023] 1 SLR 96
- [2023] 4 SLR 77
- [2023] 5 SLR 264
Cited by (3)
- W. Power Group EOOD v Mingyang Wind Power (International) Co. Ltd [2025] SGHC(I) 7
- Marketlend Pty Ltd v QBE Insurance (Singapore) Pte. Ltd. [2025] SGHC(I) 8
- Reliance Infrastructure Limited v Shanghai Electric Group Co Ltd [2024] SGHC(I) 8
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a court award more than the usual costs guidelines allow for work done before a case is transferred?
Singapore International Commercial Court · 2 August 2023 · [2023] SGHC(I) 12 -
Can an emergency arbitrator's interim award be enforced if the law of the seat gave no such power?
High Court · 11 September 2026 · [2026] SGHC 186 -
Can a court extend time to arbitrate under an insurance clause that applies once liability is admitted?
High Court · 8 September 2026 · [2026] SGHC 182 -
Does an arbitral tribunal breach natural justice by refusing to hear a defence point that was not pleaded?
High Court · 15 June 2026 · [2026] SGHC 128 -
Is an arbitral tribunal's refusal to award third-party funding costs contrary to Singapore public policy?
Singapore International Commercial Court · 2 June 2026 · [2026] SGHC(I) 5 -
Can a party that argued a new damages case on the merits later resist enforcement of the award over it?
Court of Appeal (International) · 25 May 2026 · [2026] SGCA(I) 3
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2024] SGHC(I) 5)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer