W. Power Group EOOD v Mingyang Wind Power (International) Co. Ltd

Singapore International Commercial Court

[2025] SGHC(I) 7 · SIC/OA 2/2023 ( SIC/SUM 15/2024 ) · cites 5 cases

The question

After a case moves to the international commercial court, do the High Court costs guidelines govern later costs?

The answer

No. Following the Court of Appeal, the court held there is no discernible relationship between costs under the Rules of Court and the SICC Rules, and ordered the claimant to pay $177,401.97 for the post-transfer period.

Step 1: What happened

W. Power Group EOOD (W Power) sued Mingyang Wind Power (International) Co Ltd (Mingyang) in proceedings begun on 17 June 2022 in the General Division of the High Court and transferred to the Singapore International Commercial Court by an order made on 7 March 2023, becoming Originating Application No 2 of 2023. The transfer order kept the High Court costs scale and Order 21 of the Rules of Court 2021 for costs incurred before the transfer.

By judgment dated 15 October 2024, reported as [2024] SGHC(I) 29, the court struck out W Power's Statement of Claim, refused leave to amend, dismissed the claim and ordered W Power to pay Mingyang's costs. The parties could not agree the amount, so they filed written submissions and the court decided costs without an oral hearing. Mingyang claimed $54,285 for the pre-transfer period and $171,955 for the post-transfer period, along with Hong Kong counsel's fees in renminbi, Bulgarian counsel's fees of €7,240 and disbursements of $10,189.80. W Power offered $10,000 for pre-transfer costs and $20,000 for post-transfer costs, relying on the Appendix G guidelines.

Step 2: What the court had to decide

  1. Whether pre-transfer costs should be assessed from the Appendix G ranges and whether an uplift was warranted.
  2. Whether Appendix G governed post-transfer costs under the SICC Rules and whether the costs of the strike-out and amendment summons were reasonable.
  3. Whether Mingyang's foreign counsel's fees were reasonably incurred.

Step 3: How the court reasoned

For the pre-transfer period, the court followed Kiri Industries Ltd v Senda International Capital Ltd and another [2022] 3 SLR 174, approved on this point by the Court of Appeal: Appendix G is the starting point but the complexity of a case may justify an uplift. The guideline range for matters settled at the pleading stage was $5,000 to $14,000. An uplift was justified because the claim was substantial, concerned events ten years before the suit, required investigation of Bulgarian wind power regulations and liaison with Bulgarian counsel, and involved preparing for four case management hearings. The court applied a 50% uplift to the top of the range and awarded $21,000.

For the post-transfer period, the court held that W Power relied too heavily on Appendix G. As the Court of Appeal noted in Senda International Capital Ltd v Kiri Industries Ltd [2023] 1 SLR 96, there is no discernible link between costs under the Rules of Court and under the SICC Rules, where a successful party recovers costs sensibly and reasonably incurred, subject to proportionality and reasonableness. Once the successful party gives a sufficient breakdown, the evidential burden moves to the losing party. Mingyang gave a detailed schedule of time and hourly rates; W Power challenged none of the items and filed no schedule of its own despite the court's direction. The $121,910 for SUM 15 was reasonable, as it involved a strike-out contested to the hearing and an amendment application with a complex pleading that sought to join a non-consenting claimant. However, the $30,665 for case management and $17,395 for particulars were together excessive, and the court allowed $37,000 for that work, alongside the undisputed security costs and $1,895 for the co-counsel registration.

On foreign counsel, the court accepted that Mingyang was not Singapore-based but was not satisfied the pre-transfer Hong Kong counsel's fees of RMB99,154.50 were reasonably incurred for the proceedings, allowing RMB50,000, while the post-transfer RMB5,452 was allowed in full. The Bulgarian counsel's fees were allowed because the Bulgarian regulatory regime and the changes that made the project unprofitable had to be understood.

From the judgment

“there is no discernible relationship between the quantum of costs that may be ordered under the Rules of Court and those ordered under the SICC Rules”

[2025] SGHC(I) 7 at [29]

Step 4: The order

The court ordered W Power to pay Mingyang's costs of $21,000 for the pre-transfer period and $177,401.97 for the post-transfer period, comprising $121,910 for SUM 15, $45,212.17 for the balance of the work and $10,189.80 in disbursements. It also allowed RMB55,452 for Hong Kong counsel and €7,240 for Bulgarian counsel, and ordered costs of the assessment of $5,000 plus $270 in disbursements.

Terms in this case

Evidential burden
The obligation on a party to produce enough evidence to raise an issue or to answer the case made against it. Unlike the legal burden of proof, it can shift between the parties as the evidence develops during a trial.

Court record

Key facts

Court Singapore International Commercial Court
Decided
Judge Thomas Bathurst
What the case was about Civil Procedure

Source: [2025] SGHC(I) 7, Singapore International Commercial Court, decided — eLitigation. Updated .

Judge

Parties

Cases cited (5)

SLR (3)
  • [2022] 1 SLR 88
  • [2022] 3 SLR 174
  • [2023] 1 SLR 96

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2025] SGHC(I) 7)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer