Lim Kim Huat Building Construction Pte Ltd v LBD Engineering Pte Ltd
[2026] SGHC 28 · HC/OA 1370/2025 ( HC/SUM 3719/2025,HC/SUM 3720/2025,HC/SUM 3715/2025 ) · cites 7 cases
Must a party pay the adjudicated sum into court before challenging an order enforcing an adjudication determination?
Yes. The High Court held that such a challenge counts as setting aside the determination under s 27(5) of the SOP Act, and dismissed the unpaying contractor's late setting-aside, extension of time and stay applications.
Step 1: What happened
Lim Kim Huat Building Construction Pte Ltd was a sub-contractor to LBD Engineering Pte Ltd on a building project. Under the Building and Construction Industry Security of Payment Act 2004 (SOP Act), it made a payment claim, went to adjudication, and obtained an adjudication determination dated 14 November 2025. The total sum due under the determination was $2,201,845.80, made up of $2,173,887.30 on the payment claim and $27,958.50 as 90% of the adjudication costs. LBD paid nothing.
On 2 December 2025 the sub-contractor applied in Originating Application No 1370 of 2025 for permission to enforce the determination as a judgment, and the order was made on 3 December 2025. The enforcement order was left at LBD's registered office on 8 December 2025, where a representative stamped and signed an acknowledgment of receipt. LBD still did not pay. On 23 December 2025 it filed three summonses: SUM 3720 for an extension of time, SUM 3715 to set aside the enforcement order, and SUM 3719 to stay enforcement pending the setting-aside application. The applications were heard by the General Division of the High Court, which gave an ex tempore judgment.
Step 2: What the court had to decide
- Whether the enforcement order was served on 8 December 2025, making the setting-aside application one day late.
- Whether LBD should be granted an extension of time to apply to set aside the enforcement order.
- Whether the setting-aside application had any merit, given that LBD paid no security into court under s 27(5) of the SOP Act.
- Whether enforcement should be stayed pending the setting-aside application.
Step 3: How the court reasoned
On service, LBD said the acknowledgment was a general one, not made by an officer authorised to accept court process, and that the order only reached management on 9 December 2025. It cited no authority. Under the Rules of Court 2021 and s 387 of the Companies Act 1967, a document may be served on a company by leaving it at its registered office. Service was therefore effected on 8 December 2025, and the setting-aside application, which had to be filed within 14 days, was one day late.
On the extension of time, the delay was short but not de minimis. LBD gave no satisfactory explanation of why its internal stamp showed 9 December 2025 when it admitted receiving the documents a day earlier, and the court did not hear from the person who received them. Above all, the substantive application was hopeless, and following Lee Hsien Loong v Singapore Democratic Party [2008] 1 SLR(R) 757 an extension will generally be refused in that situation because it would be futile.
The setting-aside application was hopeless for two reasons. First, LBD had not paid the unpaid adjudicated amount into court as security. Its explanation that it was attacking only the enforcement order, not the determination itself, failed: the application sought to make the determination unenforceable, and following Lau Fook Hoong Adam v GTH Engineering & Construction Pte ltd [2015] 4 SLR 615 such a challenge counts as a setting-aside application governed by s 27(5), whose security requirement is strict. Second, there was no ground to set aside the order. LBD's argument that temporary finality meant the determination should not be enforced at all ran directly against the 'pay now, argue later' principle explained in WY Steel. Its unadjudicated Supply Debt cross-claim, quantified at approximately $362,881.81, was not a basis for setting aside an enforcement order, and in any case was a fraction of the adjudicated amount.
The stay application was moot once SUM 3715 was decided at first instance. In any event, LBD did not even try to show that the sub-contractor was insolvent or that money paid would not be recovered, which is the high threshold for a stay.
“Instead of “pay now, argue later” (WY Steel at [20]), the defendant would like to pay nothing until all the arguments have been made, and the parties’ disputes finally determined.”
[2026] SGHC 28 at [39]
Step 4: The order
The High Court dismissed all three of LBD's applications, SUM 3720, SUM 3715 and SUM 3719. LBD was ordered to pay the sub-contractor costs of $12,000 and disbursements of $473.65 for SUM 3715, costs of $2,000 for SUM 3720 and costs of $3,000 for SUM 3719.
The order in the court's words
Application dismissed“For the above reasons, the claimants’ applications by SUM 3720, SUM 3715, and SUM 3719 are all dismissed.”
Source: [2026] SGHC 28, High Court, decided 9 February 2026. Read directly from the judgment.
Terms in this case
- Adjudication determination
- The decision of an adjudicator on a payment claim under Singapore's security of payment law for the building industry. It must be paid promptly, but the underlying dispute can still be finally decided later in court or arbitration.
- Security of payment
- The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.
- Extension of time
- More time, granted by a court or allowed under a contract, to do something after the original deadline, such as filing a document or bringing an appeal, or completing building works.
- Stay of execution
- A court order that temporarily stops a judgment or order from being enforced, often while an appeal is pending. Filing an appeal does not by itself stop enforcement. In a criminal case, a sentence of imprisonment or a fine can also be stayed pending an appeal.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Andre Maniam |
| What the case was about | Civil Procedure, Building and Construction Law |
| Outcome | Application dismissed |
Source: [2026] SGHC 28, High Court, decided — eLitigation. Updated .
Judge
- Andre Maniam Delivered the judgment
Parties
- LBD Engineering Pte Ltd Defendant
- Lim Kim Huat Building Construction Pte Ltd Plaintiff
Counsel
- Allyed Gateway LLC Firm
- Amanda Koh Jia Yi
- Lee Peng Khoon Edwin
- JK Law Chambers Firm
- Vinodh s/o Visvanathan
Statutes cited
Cases cited (7)
- Newspaper Seng Logistics Pte. Ltd. v Chiap Seng Productions Pte Ltd [2023] SGHC(A) 5
- [2008] 1 SLR(R) 757
- [2013] 3 SLR 380
- [2015] 4 SLR 615
- [2016] 4 SLR 626
- [2017] 1 SLR 890
- [2017] 5 SLR 640
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can attempts to resolve a complaint through an MP and government offices excuse a late judicial review application?
High Court · 17 June 2026 · [2026] SGHC 130 -
Can bankrupts' difficulty raising security for an appeal justify a long delay in seeking to appeal?
High Court (Appellate Division) · 18 March 2026 · [2026] SGHC(A) 8 -
Should a party seek a declaration that it needs no permission to appeal when the law is settled?
Court of Appeal · 26 November 2025 · [2025] SGCA 53 -
Does time to appeal run before disputed sums a trial judge left for agreement are settled?
High Court (Appellate Division) · 12 September 2025 · [2025] SGHC(A) 19 -
Will the High Court always extend the time for a medical complaints committee's inquiry?
High Court · 1 August 2025 · [2025] SGHC 148 -
Can a lawyer's basic filing mistakes count against a client seeking more time to appeal?
Court of Appeal · 23 May 2025 · [2025] SGCA 24
Referenced in
Statutes interpreted in this judgment
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC 28)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer