Zhao Yang Geotechnic Pte Ltd v China Communications Construction Company Ltd (Singapore Branch) [2026] SGHC 82 resolved a long-standing controversy in Singapore's construction adjudication landscape: whether a review adjudicator or panel may revisit the entire adjudication determination (the "Broad Interpretation") or only those issues raised by the party seeking review (the "Narrow Interpretation"). Decided on 13 April 2026 by Wong Li Kok, Alex J, the dispute arose from subcontract works performed by Zhao Yang Geotechnic Pte Ltd at Singapore Changi Airport for main contractor China Communications Construction Company Ltd. Zhao Yang applied to set aside an adjudication review determination, and Wong Li Kok J seized the opportunity to resolve the interpretive divide that had split adjudication practitioners since the Building and Construction Industry Security of Payment (Amendment) Act 2018 (Act 47 of 2018) took effect. The judgment also engages the Arbitration Act and the Interpretation Act in its statutory construction analysis.
Summary
Zhao Yang Geotechnic Pte Ltd, a subcontractor engaged for works at Changi Airport, applied to set aside an adjudication review determination under the Building and Construction Industry Security of Payment Act, raising the key question of whether a review adjudicator may review the entire adjudication determination or only those issues identified by the applicant. The adjudicated amount under the underlying payment claim was S$3,541,361.21. The High Court rejected the broad interpretation, holding that the narrow interpretation was correct, and instead of setting aside the review determination, remitted it back to the review adjudicators to consider the issues identified by the applicant.
What interpretive question did [2026] SGHC 82 resolve about SOPA adjudication reviews?
Wong Li Kok J decided on 13 April 2026 whether a review adjudicator under the Building and Construction Industry Security of Payment Act may examine the entire original adjudication determination or only the issues identified by the review applicant. The judgment resolved this divide that had existed since the 2018 amendment to the Act.
What construction project was at the centre of Zhao Yang Geotechnic v China Communications Construction [2026] SGHC 82?
The dispute arose from subcontract works at Singapore Changi Airport. China Communications Construction Company Ltd (Singapore Branch) had engaged Zhao Yang Geotechnic Pte Ltd as its subcontractor, and a payment dispute under the Security of Payment Act led to an adjudication and subsequent review determination which Zhao Yang sought to set aside.
Statutes Cited
Cases Cited (6)
Judgment
Read the full judgment on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC 82)