PS 23 Interior Pte. Ltd. v Andrew Tan Tong Sin
[2026] SGMC 71 · MC/OC 3730/2025 · cites 1 case
Must a homeowner pay a renovation company for variation works priced only after they were done?
No, here. Agreeing to works is not agreeing their price, and silence proves no agreement; allowing the company's claim in part, the court awarded $13,664.13 after setting off $8,890 for omitted works, dismissing the homeowner's counterclaim.
Step 1: What happened
PS 23 Interior Pte. Ltd., a renovation and interior design company, sued its former client Andrew Tan Tong Sin in Magistrate Court Originating Claim No 3730 of 2025 for $31,604.13 said to be unpaid under two invoices, Invoice 22003 and Invoice 23004. The works were done at his landed property at Old Upper Thomson Road under a quotation dated 23 September 2021, later varied at least three times. Ms Jackie Ong, the interior designer, gave evidence for the company.
The defendant denied that all the works were completed. He counterclaimed $59,271.40 for rectifying 12 alleged defects and $15,065 for works paid for but later dropped. A central dispute was that two materially different versions of the second variation order existed: the one he had received, and the one the company first produced with Ms Ong's affidavit, which gave him smaller credits for omitted works. The company also relied on his email of 20 April 2023 saying "these are the valid amounts" as an acceptance of Invoice 22003. Invoice 23004 billed $14,400 for further variation items, including larger bathroom tiles, cleaning and plumbing work after the property's pipes were found choked with cement and a bottle cap.
Step 2: What the court had to decide
- Which version of the variation orders accurately recorded the agreed variations and omitted works, and whether the unpleaded discrepancy could be considered.
- How much the defendant owed under Invoice 22003 and Invoice 23004.
- Whether the company breached the contract or was otherwise liable for the 12 alleged defects.
Step 3: How the court reasoned
The judge considered the unpleaded discrepancy between the two versions, citing How Weng Fun v Sengkang Town Council [2023] SGCA 21, because it would be clearly unjust not to, and the company had a fair chance to address it. Its documents were described as messy and confused, and Ms Ong conceded the omissions and variation orders were "a bit not right". The company was entitled to the variation sums the defendant accepted, but failed to prove a $200 washing machine kerb. Ms Ong admitted that certain wet kitchen items and three Omission 2 items were not done, and her explanations were unconvincing, so the defendant's version was more accurate and he was owed further credits of $2,240 and $6,650. The email did not prove acceptance: there was no evidence the invoice was attached, and "the valid amounts" implied some amounts were not valid. A $3,800 item said to be payable to Ms Ong personally could not be claimed by the company, which is a separate legal person, and arithmetic errors on the invoice were corrected.
On Invoice 23004, the company recovered the undisputed items, the trash bag charge (the defendant not having challenged it in cross-examination, as Browne v Dunn requires) and the plumbing, ceiling and paint works, as the defendant could not prove the company's contractors caused the choke. Charges for larger master bathroom tiles and a third cleaning failed because the defendant was told the price only after the work; silence does not prove agreement on price. The common bathroom tile charge failed for want of proof.
Each alleged defect failed. Several had no contractual basis, such as moving toilet pipes, access panels, electrical points, a digital lock, roof waterproofing and main water pipes. Others were unproved: photographs could not show ponding over time, the cause of outdoor wall damage needed expert evidence, the location of a damaged tile was disputed, and the handrail's agreed colour and whether it had been stained were unproved. Liability for other contractors' work was not argued.
“An agreement to carry out works is not the same as an agreement on the price of these works.”
[2026] SGMC 71 at [78]
Step 4: The order
District Judge Tay Jingxi allowed the claim in part, awarding $13,664.13, made up of $4,314.13 under Invoice 22003 and $9,350 under Invoice 23004. Having already set off $8,890 in further credits for omitted works, the judge dismissed the counterclaim. Costs were to be agreed or addressed in written submissions.
The order in the court's words
Claim allowed in part“In sum, the claim is allowed in part, in the sum of $13,664.13.”
Source: [2026] SGMC 71, Magistrates' Court, decided 12 June 2026. Read directly from the judgment.
Terms in this case
- Variation order
- An instruction issued under a construction contract that changes the work to be done, by adding, removing or altering parts of it. It usually leads to an adjustment of the contract price or time for completion.
- Set-off
- The setting of a sum one party owes another against a sum owed in the other direction, so that only the balance is payable. Its forms include legal set-off between mutual debts, equitable set-off between closely connected claims, and set-off in insolvency, as well as set-off agreed by contract.
- Counterclaim
- A claim that a defendant brings against the claimant in the same proceedings, rather than starting a separate action. The court can decide the claim and the counterclaim together.
- Pleadings
- The formal written documents in which each party to a civil case sets out the facts it relies on, such as the statement of claim and the defence. They define the issues the court has to decide.
- Expert evidence
- Opinion evidence from a person with specialised knowledge gained through training, study or experience, given to help the court on matters outside ordinary knowledge. Under the Evidence Act 1893 such opinion is relevant, but the court decides how much weight to give it, and an expert owes a duty to assist the court impartially.
Court record
Key facts
| Court | Magistrates' Court |
|---|---|
| Decided | |
| Judge | Tay Jingxi |
| What the case was about | Contract, Tort, Building and Construction Law |
| Outcome | Claim allowed in part |
Source: [2026] SGMC 71, Magistrates' Court, decided — eLitigation. Updated .
Judge
- Tay Jingxi Delivered the judgment
Parties
- PS 23 Interior Pte. Ltd. Claimant
- Andrew Tan Tong Sin Defendant
Counsel
Statutes cited
Cases cited (1)
- How Weng Fan and others v Pasir Ris-Punggol Town Council [2023] SGCA 21
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a side letter varying a subcontract leave only an expired warranty for defects found later?
High Court · 20 September 2023 · [2023] SGHC 264 -
Can an investor get substantial damages for a broken promise to restore a trading account without proving its balance?
District Court · 25 August 2026 · [2026] SGDC 272 -
Can a seller recover extra share sale money under an alleged oral side deal a decade later?
High Court · 14 July 2026 · [2026] SGHC 144 -
Can a property owner rely on an alleged oral promise to defer an agent's commission under a written agency agreement?
Magistrates' Court · 23 January 2026 · [2026] SGMC 12 -
Can a business that has no customers yet sue for passing off?
High Court · 30 September 2025 · [2025] SGHC 187 -
Are losses from employees' lawfully given notice caused by breaches committed only once they join a competitor?
High Court (Appellate Division) · 9 September 2025 · [2025] SGHC(A) 17
Referenced in
Statutes interpreted in this judgment
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGMC 71)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer