DGE v DGF

High Court

[2024] SGHC 107 · HC/OA 1165/2023 · cites 24 cases · cited by 5 cases

The question

Is a party denied a fair hearing when the tribunal raises a new issue and invites submissions on it?

The answer

No. The High Court held the seller had that opportunity but chose to wait and see rather than seek further evidence, then argued the point fully in its briefs, and dismissed its application to set aside the award.

Step 1: What happened

DGE (E) manufactured photovoltaic (solar) modules and sold them to DGF (F) under a 2012 contract and a 2013 contract, both governed by Singapore law and the CISG, with arbitration clauses. The 2013 contract appended E's "Limited Warranty", which contained an exclusion clause (cl 4) and a clause referring warranty-claim disputes to a testing institute (cl 8). F sold the modules on to group companies, which installed them on house rooftops. In late 2017 F found that the backsheets had cracked.

F began two arbitrations, later consolidated, on 23 November 2018, claiming that the modules with AAA backsheets were defective. On the first day of the liability hearing in October 2022 the tribunal raised whether the Limited Warranty was a warranty for end-users rather than one operating between E and F. On the last day F adopted that view and dropped its Limited Warranty claim. The issue went into the list of issues the tribunal settled and the post-hearing briefs.

In a partial award dated 17 August 2023 the tribunal held that the Limited Warranty was a third-party warranty, so cl 4 could not bar F's CISG claims; that it had jurisdiction; and that 365,000 AAA modules were inherently defective, being neither durable nor safe, in breach of Art 35(2) of the CISG. Remedies were left to a later phase. E applied in Originating Application No 1165 of 2023 to set the award aside on eight grounds.

Step 2: What the court had to decide

  1. Whether cl 8 of the Limited Warranty deprived the tribunal of jurisdiction.
  2. Whether E was denied a reasonable opportunity to address the third-party warranty issue, or the issue lay outside the submission to arbitration.
  3. Whether the tribunal acted improperly in its treatment of cl 5.3 of the 2013 contract and of durability under the CISG.
  4. Whether the tribunal failed to consider E's arguments on sampling, the absence of a recall, electrical safety factors, and system design and microclimate.

Step 3: How the court reasoned

On jurisdiction, decided afresh by the court, cl 8 read with the rest of the Limited Warranty applied only to claims made under that warranty. F's CISG, sale of goods, negligence and misrepresentation claims, the legal questions about the warranty, and the independent-warranty point all fell outside cl 8 and within the widely framed arbitration clauses.

On the main ground, all three arbitrators put the third-party warranty issue in play on the first day and directed both sides to address it, as in JVL Agro. E chose to wait and see, never applied to call further evidence, and argued the point fully in its briefs. A party that fails to take an available opportunity has not been denied one. Because F merely abandoned a claim, while E relied on the warranty for its own defence, F did not need to amend its pleadings; CAJ and Phoenixfin, which involved new fact-based defences raised late, were distinguished. Nor was there prejudice: the negotiation history was already in evidence, subjective intent is irrelevant to interpretation, and F's dealings with end-users could not be used. The issue was within the submission to arbitration, and the procedural order allowing new points with leave was not breached.

The tribunal's reading of cl 5.3 as not covering latent defects flowed from E's own pleaded argument and could not have changed the result. Durability was in play from the start, appeared in the settled list of issues, and was an alternative to the safety finding in any event.

The remaining complaints failed because the award showed the tribunal had noted and rejected E's points on sampling and safety; its silence on the recall point reflected a science-based view that F's conduct was irrelevant; and treating system design and microclimate as matters for the remedies phase was a merits decision. Citing CVV and others v CWB [2024] 1 SLR 32, the judge held that any inadequacy of reasons was at most an error of law, and no prejudice was shown.

From the judgment

“In my view, there is a qualitative difference between a party advancing a new claim, defence or positive case, and a party abandoning a claim along with the premises underlying that claim.”

[2024] SGHC 107 at [94]

Step 4: The order

Kristy Tan JC dismissed the application, declining to set aside the award on any of the eight grounds. Costs were left for the parties to agree or address in brief written submissions.

Terms in this case

Natural justice
The basic rules of fair procedure that a court, tribunal or other decision-maker must follow: each side must have a fair chance to be heard, and the decision-maker must not be biased or appear to be biased.
Arbitral award
The decision of an arbitral tribunal on the dispute or part of it. It binds the parties, can be enforced with the court's permission like a court judgment, and can be set aside only on limited grounds.
Arbitration agreement
An agreement, usually a clause in a contract, by which the parties agree to send their disputes to arbitration instead of to the courts. A court will generally stay court proceedings brought in breach of it.
Exclusion clause
A contract term that excludes or limits a party's liability, for example for breach of contract or negligence. Courts read such clauses strictly against the party relying on them, and statute may make them subject to a reasonableness test or render them void.

Court record

Key facts

Court High Court
Decided
Judge Kristy Tan
What the case was about Arbitration

Source: [2024] SGHC 107, High Court, decided — eLitigation. Updated .

Judge

Parties

  • DGE Claimant
  • DGF Defendant

Counsel

Counsel for the defendant
Counsel for the claimant

Statutes cited

Cases cited (24)

SLR (23)
  • [2007] 1 SLR(R) 597
  • [2007] 3 SLR(R) 86
  • [2011] 3 SLR 414
  • [2011] 4 SLR 305
  • [2013] 1 SLR 125
  • [2013] 4 SLR 972
  • [2015] 3 SLR 154
  • [2015] 3 SLR 488
  • [2016] 1 SLR 549
  • [2016] 2 SLR 1083
  • [2016] 4 SLR 768
  • [2018] 2 SLR 532
  • [2019] 2 SLR 295
  • [2021] 2 SLR 235
  • [2022] 1 SLR 1080
  • [2022] 1 SLR 47
  • [2022] 1 SLR 505
  • [2022] 2 SLR 1
  • [2022] 2 SLR 23
  • [2022] 2 SLR 557
  • [2022] 4 SLR 158
  • [2023] 1 SLR 55
  • [2024] 1 SLR 32

Cited by (5)

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Referenced in

Statutes interpreted in this judgment

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 107)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer