Turms Advisors APAC Pte. Ltd. v Steppe Gold Limited

High Court

[2024] SGHC 174 · HC/OC 77/2023 · cites 48 cases (37 Singapore, 11 foreign) · cited by 3 cases

The question

Is a clause charging a monthly retainer until the client supplies information a penalty?

The answer

Not this one. The High Court held the clause in this mandate letter was a conditional primary obligation, so the penalty rule was not engaged, and allowed the claim in part, awarding US$120,000 but refusing the success fee.

Step 1: What happened

Turms Advisors APAC Pte Ltd, a Singapore corporate finance advisory firm, was engaged by Steppe Gold Ltd, a Toronto-listed company producing precious metals in Mongolia, under a Mandate Letter executed on 24 October 2020. Turms was to act as exclusive financial adviser for a US$50m to US$80m debt financing for the expansion of its Altan Tsagaan Ovoo property. It was entitled to milestone retainer fees, including a monthly retainer of US$10,000 under cl 6(e) if the client did not provide the information needed for the Investor Financial Model within 30 days, and a success fee of 2.50% of deal value in the event of a Transaction. The mandate was extended by an Extension Letter dated 3 June 2021. Steppe Gold then secured the US$65m TDB Facility from the Trade & Development Bank of Mongolia, with which Turms had no contact, and ended the engagement in March 2022.

In Originating Claim No 77 of 2023, Turms claimed a success fee of US$1,625,000.00, the cl 6(e) retainer of US$120,000.00, late payment interest and a contractual indemnity for costs. Steppe Gold said Turms was not the effective cause of the facility, that the parties had agreed to exclude it, and that cl 6(e) was a penalty.

Step 2: What the court had to decide

  1. Whether Turms was entitled to the success fee on the US$65m TDB Facility, including whether an effective cause term applied and whether the facility had been excluded by oral agreement
  2. Whether Turms was entitled to the cl 6(e) monthly retainer fee, or whether that clause was a penalty or unsupported by consideration
  3. Whether Turms was entitled to contractual late payment interest at 10% per annum
  4. Whether Turms was entitled to a contractual indemnity for its costs of the suit

Step 3: How the court reasoned

On the success fee, the court held that the facility fell within the definition of Transaction, and that the Mandate Letter contained no express or implied effective cause term. The fee was payable simply in the event of a Transaction, and a deeming provision in cl 4 meant Turms could be paid even without introducing the investor, which was inconsistent with implying such a term. However, relying on Charles Lim, a no oral modification clause only raises a rebuttable presumption. Mr South's contemporaneous email of 16 June 2021 recorded that the TDB borrowing was agreed to be out of scope, and Turms did not object, did not seek involvement in the TDB negotiations, marketed for a larger sum, and invoiced the fee only after termination. The court found compelling evidence of an oral agreement excluding the facility, admissible under the proviso in s 94 of the Evidence Act 1893, and alternatively an estoppel by convention. Quantum meruit failed because cl 2.3 governed additional services and Steppe Gold was not enriched.

On cl 6(e), the court held it imposed a conditional primary obligation to pay for Turms standing ready on retainer, so the penalty rule was not engaged, and in any event the sum was not extravagant. Being available and forgoing other work was sufficient consideration. As cl 6(e) left the question to Turms' determination, sufficient information meant the final draft feasibility study, provided on 8 November 2021, and Steppe Gold's lawyers had earlier said it was prepared to pay this sum.

The 10% interest rate was not shown to be a penalty, given Mongolian lending rates of 9% and 11%, and Turms had not waived interest by mere inaction. The indemnity clause covered costs arising from Steppe Gold's breach, so it applied to the heads on which Turms succeeded.

From the judgment

“The outcome of this interpretation is that the claimant would be entitled to a free lunch. But it is not for the court to imply an effective cause term to prevent that outcome.”

[2024] SGHC 174 at [74]

Step 4: The order

The High Court allowed the claim in part. Turms was not entitled to the success fee or to quantum meruit, but was awarded the cl 6(e) retainer fee of US$120,000, late payment interest at 10% per annum on the cl 6(b) and cl 6(e) retainer fees, and a contractual indemnity for costs and expenses connected with the issues on which it succeeded. The court said it would hear the parties on interest and costs unless agreed.

Terms in this case

Penalty clause
A contract term requiring a party in breach to pay a sum that is not a genuine pre-estimate of the likely loss but is meant to deter breach. Singapore courts apply the rule only to sums payable on breach and will not enforce such a clause, leaving the innocent party to prove its actual loss.
Implied term
A term not expressly stated in a contract but treated as part of it, either because the law, a statute or custom implies it into all contracts of that kind, or because it is needed to fill a gap the parties did not foresee.
Estoppel
A rule that stops a person from going back on a position taken, by words, conduct, an agreed assumption or an earlier judgment, where it would be unjust to allow it, often because another person has relied on that position.
Quantum meruit
Latin for "as much as he has deserved": a claim for a reasonable sum for work done or services supplied, either under a contract that fixes no price or, where there is no enforceable contract, as a claim in unjust enrichment.
Indemnity
A promise by one person to make good another's loss or liability arising from a stated event, such as a claim by a third party. The word also describes a right to be reimbursed that the law gives in some relationships, such as an agent's right against the principal.

Court record

Key facts

Court High Court
Decided
Judge Wong Li Kok, Alex
What the case was about Contract, Agency

Source: [2024] SGHC 174, High Court, decided — eLitigation. Updated .

Judge

Parties

  • Steppe Gold Ltd Defendant
  • Turms Advisors APAC Pte Ltd Claimant

Counsel

Statutes cited

Cases cited (48)

SG (5)
SLR (32)
  • [1992] 3 SLR(R) 503
  • [1994] 3 SLR(R) 804
  • [1996] 1 SLR(R) 14
  • [1997] 1 SLR(R) 811
  • [1999] 1 SLR(R) 755
  • [2000] 2 SLR(R) 407
  • [2004] 3 SLR(R) 73
  • [2007] 2 SLR(R) 230
  • [2007] 2 SLR(R) 655
  • [2007] 3 SLR(R) 537
  • [2008] 2 SLR(R) 474
  • [2009] 2 SLR(R) 332
  • [2012] 2 SLR 1
  • [2012] 4 SLR 1206
  • [2013] 3 SLR 666
  • [2013] 4 SLR 193
  • [2014] 1 SLR 860
  • [2015] 4 SLR 1019
  • [2016] 4 SLR 728
  • [2016] 5 SLR 848
  • [2017] 1 SLR 219
  • [2017] 1 SLR 546
  • [2018] 1 SLR 170
  • [2018] 1 SLR 180
  • [2018] 1 SLR 317
  • [2018] 1 SLR 979
  • [2019] 1 SLR 696
  • [2020] 1 SLR 896
  • [2020] 2 SLR 200
  • [2020] 5 SLR 514
  • [2021] 2 SLR 153
  • [2023] 1 SLR 922
UK (9)
  • [1915] AC 79
  • [2008] 1 WLR 909
  • [2008] EWCA Civ 419
  • [2009] EWHC 713
  • [2010] EWHC 676
  • [2011] EWHC 103
  • [2014] EWHC 1282
  • [2014] EWHC 2165
  • [2021] EWCA Civ 844
HK (2)
  • [2019] HKCA 606
  • [2020] HKCFA 38

Cited by (3)

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Referenced in

Statutes interpreted in this judgment

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 174)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer