Reformd Pte Ltd v Kopigi Pte Ltd
[2026] SGHC 175 · HC/OC 483/2024 · cites 11 cases (10 Singapore, 1 foreign) · cited by 1 case
What can a client recover when a designer ends their contract without the required notice?
Only nominal damages, here, as no loss was proved. Allowing the claim in part, the High Court awarded S$500 for wrongful termination without a week's notice, rejected the other claims, and dismissed the designer's counterclaim.
Step 1: What happened
Reformd Pte Ltd planned a shop selling mechanical keyboards and engaged Kopigi Pte Ltd, an interior design firm, under a consultancy agreement executed on 22 February 2024 to prepare a concept design and a schematic design. The agreement named a unit at GR.iD in Selegie, but Reformd took a unit at Cineleisure Orchard instead, with a rent-free fitting-out period from 1 April 2024 to 31 May 2024. The agreement allowed either party to end the appointment on one week's written notice and said time was of the essence wherever time was mentioned; it set no completion date.
The landlord sent a fit-out guide on 8 March 2024. Kopigi's designs were sent to the landlord by Reformd's contractor on 26 March 2024 and rejected the next day, with new height limits and cross-visibility comments; the landlord later told the parties to disregard the guide. After a meeting on 5 April 2024 the parties agreed on a revised timeline, but tension continued. On 15 April 2024, after Reformd's side raised legal action, Kopigi's director wrote in a WhatsApp group, and then by email, that Kopigi would "terminate this contract henceforth". The shop opened later than Reformd wanted. In Originating Claim No 483 of 2024 Reformd claimed S$462,907.56, alleging breaches of obligations of "porosity" and expedition and wrongful termination. Kopigi counterclaimed S$101,896.36 for work done.
Step 2: What the court had to decide
- Whether the agreement contained an express or implied term that the design meet a porosity requirement, or that the work be done expeditiously to allow opening in June 2024, and whether any such term was breached.
- Whether Kopigi's notices of 15 April 2024 wrongfully terminated the agreement without the required week's notice, and if so what damages followed.
- Whether Kopigi could recover on its counterclaim for completed stages, additional work and acceleration costs.
Step 3: How the court reasoned
On porosity, neither the agreement nor the fit-out guide mentioned it; the guide's 2.1m limit concerned merchandise displays, which Kopigi's design met. The court was not persuaded the landlord had conveyed such a requirement at the 7 March 2024 meeting: the landlord's representative was not called, the meeting notes did not record it, and Reformd's witnesses described it differently. No term could be implied under Sembcorp Marine Ltd v PPL Holdings Pte Ltd [2013] 4 SLR 193, and in any event Kopigi kept working actively after the rejection and was never asked to deal directly with the landlord.
On expedition, the time-of-essence clause applied only where time was mentioned, and the prompt-decision clause bound the client, not the designer. Reformd's own case on the deadline shifted between 1 June, early June and the third week of June, and its witnesses could not say when any date was communicated. There was no true gap to fill, and the default duty to finish within a reasonable time sufficed. Kopigi had in any case worked through several inaccurate floor plans and delivered designs promptly.
On termination, "henceforth" meant from now on, as Kopigi's director accepted, and with an account rendered the same day and no follow-up after seven days the notices took immediate effect in breach of the notice clause. Labelling the email "without prejudice" did not make it privileged. But Reformd proved no loss: its loss-of-profit theory appeared first in closing, rested on sales data and compounded multipliers, rent and staff salaries would have been incurred anyway, and the first fee was for work already done. Nominal damages were therefore awarded.
On the counterclaim, payments due upon termination could not be claimed by the party that terminated wrongfully, since no one may profit from their own wrong. The claims for additional and accelerated work lacked any written terms, time records or rates, and quantum meruit failed for the same reasons.
“The Defendant is not an innocent party. It is the party that brought the Consultancy Agreement to a premature end by its own wrongful act.”
[2026] SGHC 175 at [106]
Step 4: The order
The court allowed the claim in part: Kopigi was liable only for wrongful termination, and Reformd was awarded nominal damages of S$500, its porosity and expediency claims failing. The counterclaim was dismissed in its entirety. Costs were to be heard separately.
Terms in this case
- Breach of contract
- A failure, without lawful excuse, to perform a contractual obligation as and when it is due. Every breach gives the innocent party a right to damages; a sufficiently serious breach may also allow it to end the contract.
- Nominal damages
- A small sum awarded where a legal right has been infringed, such as by a breach of contract or a tort actionable without proof of loss, but the claimant has not proved any real loss.
- Implied term
- A term not expressly stated in a contract but treated as part of it, either because the law, a statute or custom implies it into all contracts of that kind, or because it is needed to fill a gap the parties did not foresee.
- Counterclaim
- A claim that a defendant brings against the claimant in the same proceedings, rather than starting a separate action. The court can decide the claim and the counterclaim together.
- Quantum meruit
- Latin for "as much as he has deserved": a claim for a reasonable sum for work done or services supplied, either under a contract that fixes no price or, where there is no enforceable contract, as a claim in unjust enrichment.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | S Mohan |
| What the case was about | Contract |
Source: [2026] SGHC 175, High Court, decided — eLitigation. Updated .
Judge
- S Mohan Delivered the judgment
Parties
- Kopigi Pte Ltd Defendant
- Reformd Pte Ltd Plaintiff
Counsel
Cases cited (11)
- [2017] SGHC 313
- [2000] 3 SLR(R) 386
- [2006] 4 SLR(R) 807
- [2007] 2 SLR(R) 433
- [2008] 2 SLR(R) 623
- [2013] 4 SLR 193
- [2023] 1 SLR 1477
- [2023] 3 SLR 1130
- [2024] 3 SLR 1049
- [2025] 2 SLR 90
- [2025] KB 311
Cited by (1)
- JFX and another v JFZ [2026] SGSCT 26
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Can a borrower avoid repaying a loan by claiming the lender overstated the value of assets sold to him?
High Court · 2 November 2026 · [2026] SGHC 228 -
Can a purchaser of a food stall business end the contract when the vendor cannot lawfully sublet the stall?
District Court · 13 October 2026 · [2026] SGDC 329 -
Can an investor get substantial damages for a broken promise to restore a trading account without proving its balance?
District Court · 25 August 2026 · [2026] SGDC 272 -
Can a company recover its trading losses from a negligent auditor?
Court of Appeal · 16 July 2026 · [2026] SGCA 33 -
Can a buyer that kept accepting late deliveries without reserving its rights later terminate for those delays?
High Court (Appellate Division) · 29 June 2026 · [2026] SGHC(A) 19 -
Is a client's refusal to make a contract's first 50% payment a repudiatory breach?
District Court · 5 May 2026 · [2026] SGDC 151
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC 175)