Rich Construction Company Pte. Ltd. v Greatearth Construction Pte Ltd (In Liquidation) and others

High Court

[2024] SGHC 144 · HC/OA 243/2023 · HC/OA 244/2023 · cites 11 cases (7 Singapore, 4 foreign)

The question

Does a deed releasing a company in liquidation from performing a contract bar earlier proofs of debt?

The answer

Not this deed. The High Court read the release as covering only performance and work from 1 September 2021, allowed both applications in part, and admitted the proofs at the liquidators' lower completion-cost figure.

Step 1: What happened

Rich Construction Company Pte Ltd and China State Construction Engineering Corporation Limited (Singapore Branch) (CSCEC), related companies, each had a joint venture agreement with Greatearth Construction Pte Ltd (GEC) for separate construction projects. GEC's share under Rich's agreement was 30%. GEC went into provisional liquidation on 31 August 2021, which took it out of the joint ventures while the projects were still being built. On 25 September 2021 Rich and CSCEC lodged proofs of debt for completion costs and termination costs.

On 31 May 2022 each signed a settlement deed with GEC's liquidators. Clause 1.5 said the deed did not cover the claims in the proofs of debt, other than "Excluded Liabilities", which would be adjudicated. Clause 1.6 released GEC from liabilities arising from any obligations to perform the contract or agreement, or anything undertaken or that ought to have been undertaken on the project, from 1 September 2021 onwards. On 9 March 2023 the liquidators rejected both proofs entirely, saying the claims were settled by the deeds and, alternatively, were not supported by documents.

Rich (Originating Application No 243 of 2023) and CSCEC (Originating Application No 244 of 2023) applied under r 132(1) of the insolvency rules to reverse or vary the decisions. CSCEC later withdrew all but a legal-costs item.

Step 2: What the court had to decide

  1. Whether clauses 1.5 and 1.6 of the settlement deeds released GEC from the liabilities claimed in the proofs of debt.
  2. Whether Rich could prove a contingent and expectation loss for completion costs, and how it should be valued.
  3. Whether the claims were sufficiently substantiated, and what amounts should be admitted.

Step 3: How the court reasoned

The court reviewed the liquidators' decisions afresh on the evidence now before it, with the burden on the creditors. On the deeds, it agreed with the claimants that the release covered only GEC's duty to perform and liability for work the claimants did from 1 September 2021, not every liability. Reading clause 1.6 as a total clean break would leave clause 1.5 with nothing to do, and the liquidators could not say what would remain to be adjudicated on that reading. The negotiation emails, treated with caution, supported the claimants: their counsel twice said the clause was not meant to release all GEC's liabilities, and his wording was accepted.

On contingent loss, s 218 of the Insolvency, Restructuring and Dissolution Act 2018 makes contingent liabilities provable and requires them to be estimated. Following In re Danka Business Systems plc, the value must rest on a genuine and fair assessment of the chances of the liability occurring.

On substantiation, the court found the evidence evenly balanced: the claim was right in principle but based on outdated figures for projects still under way, and the liquidators admitted they had not examined the thousand-page supporting affidavit in detail. Rather than make a simple yes-or-no ruling, the court adjourned for the parties to confer. They then asked it to choose between $19,175,002.00, the net liabilities in Rich's audited 2022 accounts, and $10,015,612.00, that figure after a reversal recorded in the same accounts. The court accepted that Rich's real losses might well be higher, but its later cost reports were not independently verified. With small likely dividends and voluminous documents, it was practical and reasonable for the liquidators to rely on the audited accounts. Having seen the unredacted legal invoices, the court accepted the termination costs as work done because of the termination.

From the judgment

“In short, whilst the claimants appeared to have a correct claim in principle, it was based on information which seemed outdated and remained a moving feast as the projects were in the midst of construction.”

[2024] SGHC 144 at [47]

Step 4: The order

Wong Li Kok, Alex JC allowed both applications in part. The deeds did not bar the claims and Rich could prove contingent loss, but the court accepted the liquidators' lower figure for completion costs. Rich's proof was admitted at $10,062,220.79, made up of $10,015,612.00 for completion costs and $46,608.79 for termination costs; CSCEC's was admitted at $46,608.79 for termination costs. The liquidators were directed to accept these debts and pay dividends on them. By agreement there was no order as to costs.

Terms in this case

Proof of debt
A creditor's formal written claim, with supporting documents, lodged with the liquidator, judicial manager, scheme manager or trustee in bankruptcy, so that the claim can be admitted and the creditor can vote or share in any distribution.
Liquidator
A person appointed to wind up a company, usually under the Insolvency, Restructuring and Dissolution Act 2018 or under the law of the company's home jurisdiction, who takes control of its assets, realises them, investigates its affairs, decides creditors' claims and pays them in the order the law sets, passing any surplus to the members.
Expectation loss
The loss measured by what a party would have gained had a contract been performed as promised. Damages on this basis aim to put the innocent party, as far as money can, in the position it would have been in if the contract had been performed.

Court record

Key facts

Court High Court
Decided
Judge Wong Li Kok, Alex
What the case was about Insolvency Law

Source: [2024] SGHC 144, High Court, decided — eLitigation. Updated .

Judge

Parties

  • China State Construction Engineering Corporation Limited (Singapore Branch) Claimant
  • Greatearth Construction Pte Ltd (In Liquidation) Defendant
  • Rich Construction Company Pte Ltd Claimant
  • Chan Kheng Tek Defendant
  • Sam Kok Weng Defendant

Counsel

Counsel for the claimant
Counsel for the defendant

Statutes cited

COVID-19 (Temporary Measures) Act
Insolvency, Restructuring and Dissolution Act
Restructuring and Dissolution Act

Cases cited (11)

SG (1)
  • [2022] SGHC 304
SLR (6)
  • [1997] 1 SLR(R) 923
  • [2008] 3 SLR(R) 1029
  • [2009] 3 SLR(R) 590
  • [2009] 4 SLR(R) 458
  • [2013] 2 SLR 1035
  • [2021] 4 SLR 809
UK (3)
  • [1960] 1 WLR 646
  • [2013] EWCA Civ 92
  • [2013] EWHC 92
HK (1)
  • [2005] 4 HKC 51

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 144)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer