DSQ v DSR
Catchwords
Practice Areas
Judges (1)
Counsel (12)
Parties (2)
Case Significance
DSQ v DSR [2026] SGHC 67 is a High Court General Division judgment delivered by Andre Maniam J on 31 March 2026, concerning an application by an employer (DSQ) to set aside an arbitral award issued on 2 April 2025 in favour of a contractor (DSR) arising from disputes under a design-and-build contract for a railway project. The tribunal — chaired by Sir Antony Edwards-Stuart, with Edwin Glasgow CBE QC and Harish Salve QC as co-arbitrators — issued a Decision and Addendum on 25 June 2025 before DSQ applied to court on 25 September 2025, raising a jurisdictional challenge and four natural justice grounds. The court addressed whether non-compliance with pre-arbitration procedures went to admissibility or jurisdiction, and whether the tribunal deprived DSQ of a reasonable opportunity to respond. DSQ was represented by Koh Swee Yen, Daniel Gaw Wai Ming, Ooi Shu Min, Pang Yi Ching Alessa, and Shawn Ang De Xian of WongPartnership LLP; DSR by Vellayappan Balasubramaniyam, Divyesh Menon, Ho Linming, Ku Chern Ying Vanessa, and Poon Kin Mun Kelvin of Rajah & Tann Singapore LLP.
Summary
An employer under a design-and-build contract for a railway project applied to set aside an arbitral award issued in favour of the contractor, contending that the tribunal lacked jurisdiction because the contractor had not complied with the pre-arbitration dispute resolution procedure in Clause 20 of the General Conditions of Contract, and that the tribunal had breached natural justice in four respects. The court considered whether non-compliance with the pre-arbitral procedure went to jurisdiction or admissibility, and whether any procedural irregularities had caused real prejudice. The application to set aside the award was dismissed in its entirety.
What arbitration setting-aside grounds were considered in DSQ v DSR [2026] SGHC 67?
Andre Maniam J of the High Court determined on 31 March 2026 whether an employer could set aside a 2 April 2025 arbitral award on grounds that the tribunal lacked jurisdiction and breached natural justice in four respects, including whether failure to comply with pre-arbitration procedures went to admissibility or jurisdiction.
Statutes Cited
Cases Cited (15)
Judgment
Read the full judgment on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC 67)