33Club Pte. Ltd. v Design Cliniq Pte. Ltd.
[2026] SGHC 39 · HC/OC 552/2023 · cites 10 cases
Step 1: What happened
33Club Pte Ltd, which runs a private members' club at 22 Malacca Street, engaged Design Cliniq Pte Ltd around May 2022 to renovate its premises, with no written contract. Work proceeded on a rough bill of quantities sent over WhatsApp, which the club's managing director, Mr Tan, told the contractor to "just proceed" with. When insurance was arranged, Mr Tan entered a "Contract value" of "$500k". The club paid two sums of $50,000. The club itself bought travertine fluted tiles from a supplier in China, and the contractor fixed them to the walls with adhesive. On 6 December 2022 several tiles fell, injuring a person helping the club inspect the works. The contractor refixed them with screws by 8 December 2022, and a professional engineer certified the installation safe on 18 January 2023. A door closer also came loose.
The contractor invoiced about $609,719.50 for the works and a further $92,888.31 for professional fees, drawings and project management. Under the Security of Payment Act an adjudicator awarded it $86,281.40, which the club paid. In HC/OC 552/2023 in the General Division of the High Court, the club sued in negligence over the tiles, the door closers and other alleged defects, eventually claiming losses of $1,472,818.99, including losses linked to a luxury watch trader leaving the premises. The contractor counterclaimed $513,527.42 or a reasonable sum.
Step 2: What the court had to decide
- Whether the renovation works, in particular the screw rectification of the tiles, were defective or fell below the standard of care
- Whether the adjudication determination prevented the court from reassessing the contractor's counterclaim
- Whether the contract covered labour only or labour and materials, and whether a price of $500,000 had been agreed
- What sum the club must pay for the works and the additional invoices
Step 3: How the court reasoned
On defects, the court found both sides shared blame for the original tile failure: the club bought tiles from an overseas source with no installation guidance and gave inaccurate dimensions, while the contractor did no simple pull-out test and conceded poor bonding and workmanship. The real issue was the rectification. The club knew of and engaged with the screw method, and the claim that it was only temporary was an after-thought. The court accepted the engineer's evidence, unrebutted by any engineer for the club, that the screws were safe for tiles weighing about 5kg each, and preferred the contractor's expert, since the club's expert had assumed tiles of 30kg and relied on inapplicable guidelines. No tile had fallen or cracked since. Only the visible putty around the screws was an aesthetic shortfall. The door closer evidence was sparse, and most other complaints were raised two years late, some being plainly not the contractor's responsibility.
On losses, the court found the claimed sums had ballooned, involved double counting and lacked support. It gave no weight to the watch trader's evidence, noting that Mr Tan had been a director and shareholder of that trader, which was not disclosed in his evidence, and that the trader's notice and profit figures did not fit its account.
On the adjudication, temporary finality under the Security of Payment Act means the court may decide the dispute afresh while taking account of the adjudicator's reasoning.
On the contract, materials were within scope, as the messages and invoices showed. The "$500k" figure was given to obtain insurance, not as an agreed price, and the contractor's handwritten note of rates was largely unreadable and could not found an objective agreement. A term that a reasonable price be paid was implied. The court used the competing quotation, at the lower end of the reasonable range, as that price and treated the discount from the invoice as covering the minor defects. It allowed project management fees, since the club's own case showed such services were given, but disallowed the unproven drawings and a small invoice whose figures were unexplained.
“The reality of the present case is that imperfect, but largely completed, work is still deserving of remuneration, albeit at the lower end of the spectrum.”
[2026] SGHC 39 at [155]
Step 4: The order
The court allowed the club's claim and the contractor's counterclaim in part. The claim succeeded only to the extent that there were some minor imperfections in the works, which were taken into account through a reduced price. The counterclaim succeeded to the extent that the contractor was entitled to a reasonable price for the invoiced works, based on a competing contractor's quotation of $411,786.90, plus professional fees and project management fees of $82,237.50. After credit for the two payments and the adjudicated amount, the club was ordered to pay the contractor a net global sum of $307,743. Costs were left for directions if not agreed.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Mohamed Faizal |
| What the case was about | Building and Construction Law |
Source: [2026] SGHC 39, High Court, decided — eLitigation. Updated .
Judge
- Mohamed Faizal Delivered the judgment
Parties
- 33Club Pte Ltd Plaintiff
- Design Cliniq Pte Ltd Defendant
Counsel
- H A & Chung Partnership Firm
- Chung Ping Shen
- Shaun Wong LLC Firm
- Shenton Law Practice LLC Firm
- Decruz Martin Francis
- Goh Phai Cheng
Statutes cited
Cases cited (10)
- [2014] SGHC 177
- [2017] SGHC 93
- [2000] 2 SLR(R) 407
- [2001] 2 SLR(R) 1
- [2007] 2 SLR(R) 983
- [2013] 3 SLR 380
- [2013] 4 SLR 193
- [2016] 4 SLR 728
- [2017] 1 SLR 890
- [2020] 3 SLR 373
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
Kwek Mean Luck J allowed Terrenus's claims in part, awarding nominal damages of $1,500 for each of the embedment and clearance breaches, $912 for six insufficiently ground roots and $30,600 in…
High Court · 27 November 2023 · [2023] SGHC 333 -
The Appellate Division allowed the appeal in part.
High Court (Appellate Division) · 2 January 2024 · [2024] SGHC(A) 1 -
The court allowed Pro-Active's claim in part, giving judgment for $179,151.04 with interest at 5.33% per annum from 6 November 2021 until payment, instead of the $558,559.97 claimed.
High Court · 31 July 2023 · [2023] SGHC 205 -
The court rejected DG's request to deduct the remaining sums, holding that the point had not been pleaded or run at trial.
High Court (Appellate Division) · 31 May 2023 · [2023] SGHC(A) 20 -
The court allowed Calpeda's claim for $683,147.92 with interest at 5.33% per annum from service of the writ to judgment, and dismissed Chew Construction's counterclaim in full.
High Court · 18 April 2023 · [2023] SGHC 102 -
The High Court held that the review panel was entitled, and bound, to review the entire adjudication determination, so it had misdirected itself.
High Court · 13 April 2026 · [2026] SGHC 82
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2026] SGHC 39)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer