Diamond Glass Enterprise Pte. Ltd. v Zhong Kai Construction Company Pte. Ltd.
High Court (Appellate Division)
[2023] SGHC(A) 20 · AD/CA 125/2021 · cites 4 cases (3 Singapore, 1 foreign)
Step 1: What happened
This was a supplementary judgment of the Appellate Division in cross-appeals AD/CA 125/2021 and AD/CA 129/2021. Zhong Kai Construction Co Pte Ltd (ZK) had engaged Diamond Glass Enterprise Pte Ltd (DG) by a Letter of Award dated 7 November 2016 as subcontractor for aluminium cladding, blast and ballistic doors, windows and related works for a project at Singapore Changi Airport. In Suit No 1282 of 2019, ZK claimed liquidated damages for delay and the cost of replacement and rectification works after DG left the site around 6 June 2018, and sought to overturn an adjudication determination of $197,522.83 in DG's favour. DG counterclaimed for sums under four variation orders.
In its main judgment of 23 December 2022, the court allowed both appeals in part, awarding DG the variation sums for VO 6 and VO 8 and the retention sum of $27,902.75, and adjusting ZK's rectification awards. Afterwards, DG's solicitors wrote asking the court to deal with two points: whether the value of works DG never completed, which DG put at $62,514.30, should be deducted from ZK's award; and an apparent arithmetic error in the main judgment. The parties also could not agree the costs of the appeals, and ZK asked for orders on sums held in court.
Step 2: What the court had to decide
- Whether ZK's award for replacement works should be reduced by the value of works DG left uncompleted
- Whether the calculation of DG's entitlement in the main judgment needed correction, and how
- What costs DG should receive for the two appeals
- How the sums each side had paid into court should be dealt with
Step 3: How the court reasoned
On the remaining sums, the court accepted the principle in Mertens v Home Freeholds Co [1921] 2 KB 526 that the usual measure for an unfinished building contract is the cost of completion less the unpaid contract price. But it said such claims rarely arise in so simple a form, because unfinished work is usually mixed with defective work and other losses such as lost warranties and delay. DG conceded the point was not specifically pleaded, gave no particulars, did not raise it in closing submissions and did not put it to witnesses. Without findings of fact the court could not tie DG's three figures to the evidence, and some of the related ZK claims had been dismissed anyway. The court also criticised DG's solicitors for not identifying the pleadings they relied on when asked.
On the arithmetic, the trial judge had wrongly deducted VO 18, which he had allowed, and had also mistyped a total. Adding VO 18 again, as DG proposed, would double count it, since it was already in the adjudicated sum.
On costs, the court declined to decide simply by counting issues won, and fixed amounts within the Practice Directions range. Since ZK had failed to overturn the adjudication, it was to bear 80% of the adjudication fees and pay late payment interest up to the date of decision.
“DG’s more fundamental problem, which is fatal to and undermines the whole basis of their complaint, is that this issue was not specifically pleaded.”
[2023] SGHC(A) 20 at [35]
Step 4: The order
The court rejected DG's request to deduct the remaining sums, holding that the point had not been pleaded or run at trial. It corrected the main judgment so that DG's entitlement on the adjudication stood at $197,522.83, about 74.6% of its adjudication claim. It awarded DG costs of $70,000 for CA 125 and $50,000 for CA 129 with disbursements of $18,000, and ordered ZK to pay DG 80% of the adjudication fees and late payment interest on the adjudicated amount. After set-off it ordered that $236,412.97 be paid to ZK out of DG's $541,000 in court with the balance returned to DG, that ZK's $211,044 security be returned to ZK, and that ZK's solicitors' undertaking be discharged.
Court record
Key facts
| Court | High Court (Appellate Division) |
|---|---|
| Decided | |
| Judges | Hoo Sheau Peng, Quentin Loh, Woo Bih Li |
| What the case was about | Building and Construction Law |
Source: [2023] SGHC(A) 20, High Court (Appellate Division), decided — eLitigation. Updated .
Judges
- Hoo Sheau Peng
- Quentin Loh Delivered the judgment
- Woo Bih Li
Parties
- Diamond Glass Enterprise Pte Ltd Appellant
- Zhong Kai Construction Co Pte Ltd Respondent
Counsel
- TSMP Law Corporation Firm
- Chan Kah Keen Melvin
- Yong Wei Jie Timothy
- Zenith Law Corporation Firm
- Isabel Su Hongling
- Kris Chew Yee Fong
Statutes cited
Cases cited (4)
- [2021] SGHC 277
- [2022] SGHC(A) 44
- [2021] 2 SLR 510
- [1921] 2 KB 526
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
The court allowed the club's claim and the contractor's counterclaim in part.
High Court · 20 February 2026 · [2026] SGHC 39 -
Kwek Mean Luck J allowed Terrenus's claims in part, awarding nominal damages of $1,500 for each of the embedment and clearance breaches, $912 for six insufficiently ground roots and $30,600 in…
High Court · 27 November 2023 · [2023] SGHC 333 -
The District Court allowed the claim in part.
District Court · 13 January 2026 · [2026] SGDC 23 -
The Appellate Division allowed the appeal in part.
High Court (Appellate Division) · 2 January 2024 · [2024] SGHC(A) 1 -
The court allowed Pro-Active's claim in part, giving judgment for $179,151.04 with interest at 5.33% per annum from 6 November 2021 until payment, instead of the $558,559.97 claimed.
High Court · 31 July 2023 · [2023] SGHC 205 -
The court allowed Calpeda's claim for $683,147.92 with interest at 5.33% per annum from service of the writ to judgment, and dismissed Chew Construction's counterclaim in full.
High Court · 18 April 2023 · [2023] SGHC 102
Referenced in
Statutes interpreted in this judgment
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2023] SGHC(A) 20)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer