DMC v DMD
[2025] SGHC 151 · HC/OC 868/2023 · cites 11 cases (10 Singapore, 1 foreign)
Step 1: What happened
DMC was the main contractor for a road marking project for the Employer and, by two sub-contracts dated 28 June 2021, engaged DMD to paint road markings in the East and West sectors, with contract sums of $10,186,054.00 and $9,808,289.00 respectively. DMD began physical works only around late September and early October 2021. On unchallenged evidence, it had worked at only a small fraction of the locations by the end of June 2022, more than a year in. DMC and the Employer issued repeated warnings. DMC then deployed its own staff, bought equipment and hired third parties to take over or support work at many locations, and the works, including the fifth month field tests, were substantially completed in December 2023, after the completion date of 27 June 2023.
In Originating Claim No 868 of 2023, DMC claimed six backcharges (including the costs of taking over the works, third party costs, completion work after 27 June 2023, project personnel DMD was meant to provide, help with pre-condition reports and job proposal sheets, and a 15% profit and attendance charge on earlier agreed backcharges) and liquidated damages, a net $3,391,652.86. DMD disputed its scope of work and the charges, relied on suspension under s 26 of the Building and Construction Industry Security of Payment Act 2004, said the liquidated damages clause was a penalty, alleged unjust enrichment because DMC had been paid by the Employer, and counterclaimed $533,767.18 and $679,007.94 for work done.
Step 2: What the court had to decide
- Whether DMC had to give notice of specific locations before backcharging, and what the parties agreed at their 14 June 2022 meeting about administrative charges.
- Whether the disputed expenses and amounts in the backcharges were recoverable, including whether s 26 of the Act barred the backcharge for work after 27 June 2023.
- Whether DMC was entitled to liquidated damages, or whether the clause was a penalty.
- Whether DMC's claims amounted to unjust enrichment, and whether DMD's counterclaim succeeded.
Step 3: How the court reasoned
Applying Vim Engineering Pte Ltd v Deluge Fire Protection (S.E.A.) Pte Ltd [2023] SGHC(A) 2, the backcharge clause contained no notice requirement, any lack of notice would not extinguish the general right to damages, and DMD had in any case been warned many times that DMC would step in. Its witness's claim that DMD could have caught up was badly shaken in cross-examination. On the meeting minutes, DMD's own witness said the waiver of administrative charges covered only backcharges already agreed, and although the 15% charge recorded there referred to third parties, that did not displace DMC's contractual right to profit and attendance.
The court accepted that depreciation on equipment bought to take over the work, dormitory, refreshment and other worker costs were reasonable and not duplicated. DMD bore the burden of proving the third party backcharge excessive and its director's later unaccompanied measurements did not displace figures the Employer had verified. Applying Audi Construction Pte Ltd v Kian Hiap Construction Pte Ltd [2018] 1 SLR 317, DMD waived suspension by election when it carried on the field tests and counterclaimed for them. The personnel clauses referring to the Contractor, carried over unchanged from the main contract, meant DMD, and DMC's email told DMD to stop only at specific locations.
The fifth month field tests were within the scope to be completed by 27 June 2023, and the delay was due to DMD's lack of resources. Distinguishing Denka Advantech Pte Ltd and another v Seraya Energy Pte Ltd and another and other appeals [2021] 1 SLR 631, the daily rate was triggered only by late completion and matched or was slightly below the main contract rate, so it was a genuine pre-estimate and not a penalty; actual loss need not be shown. Payment by the Employer arose under a separate bargain and was no windfall. The counterclaim for field tests lacked any supporting reports, and no retention sum was pleaded.
“If it was not possible to complete the works by the contractual timeline of 27 June 2023, this was very much due to how DMD had mismanaged its obligations under the Sub-Contracts.”
[2025] SGHC 151 at [118]
Step 4: The order
The court allowed DMC's claims for all six backcharges and for liquidated damages of $888,300 (excluding GST), and dismissed DMD's counterclaim. It awarded DMC pre-judgment interest at 5.33% per annum from the dates DMC proposed, less interest on the value of completed sub-contract work, post-judgment interest at the same rate, and costs.
Court record
Key facts
| Court | High Court |
|---|---|
| Decided | |
| Judge | Kwek Mean Luck |
| What the case was about | Contract, Building and Construction Law |
Source: [2025] SGHC 151, High Court, decided — eLitigation. Updated .
Judge
- Kwek Mean Luck Delivered the judgment
Parties
- DMC Plaintiff
- DMD Defendant
Counsel
- Dentons Rodyk & Davidson LLP Firm
- Ang Wei Jing, Sheryl
- Kirindeep Singh
- Pang Haoyu, Samuel
- Justicius Law Corporation Firm
- Elizabeth Toh Guek Li
- Lazarus Nicholas Philip
Statutes cited
Cases cited (11)
- Pro-Active Engineering Pte. Ltd. v Prime Structures Engineering Pte Ltd [2023] SGHC 205
- Sunrise Industries (India) Ltd v PT. Oki Pulp & Paper Mills and another [2023] SGHC 3
- Vim Engineering Pte Ltd v Deluge Fire Protection (S.E.A.) Pte Ltd [2023] SGHC(A) 2
- PT. Oki Pulp & Paper Mills v Sunrise Industries (India) Ltd [2023] SGHC(A) 38
- [2020] SGHC 165
- [2004] 3 SLR(R) 288
- [2008] 2 SLR(R) 623
- [2016] 3 SLR 1308
- [2018] 1 SLR 317
- [2021] 1 SLR 631
- [2021] EWHC 2207
Related cases
Other Singapore judgments on the same subject, most closely matched first.
-
The court dismissed the Landlord's application in OA 1147 and granted the Tenant's application in OA 1207.
High Court · 30 January 2024 · [2024] SGHC 27 -
District Judge Tay Jingxi allowed the claim in part, awarding $13,664.13, made up of $4,314.13 under Invoice 22003 and $9,350 under Invoice 23004.
Magistrate Court · 12 June 2026 · [2026] SGMC 71 -
The High Court allowed the application.
High Court · 24 June 2025 · [2025] SGHC 114 -
The Appellate Division allowed the appeal in part: it allowed Tuffi's claim against Techkon, rectifying the 2019 agreement so that the adjusted final sum was $1,452,962.89 and ordering Techkon to pay…
High Court (Appellate Division) · 8 October 2026 · [2026] SGHC(A) 25 -
The High Court allowed the claim and awarded Stamford Land $1,887,946.31 for its legal costs, with costs of the action and interest at 5.33% per annum from the date of judgment.
High Court · 29 September 2026 · [2026] SGHC 202 -
The District Court dismissed the claimant's claim, holding that ECCM coverage was not engaged where the insured underwent endovascular repair and that she was bound by that definition.
District Court · 3 September 2026 · [2026] SGDC 276
Referenced in
Legal concepts and references
Read the full judgment
The judgment itself is on the official Singapore Courts portal.
Read on eLitigationSource: eLitigation ([2025] SGHC 151)
This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer