The question

Can a contractor stop an employer calling on a performance bond over disputed delay damages and works?

The answer

Not here. The High Court found no strong prima facie case of unconscionability, since the disputes were bona fide contractual ones, saw no basis to reduce the call, and dismissed the application and a later Erinford injunction application.

Step 1: What happened

Shanghai Chong Kee Furniture & Construction Pte Ltd, the claimant contractor, agreed on 19 August 2019 to carry out restoration works at the Church of St Teresa for a contract sum of $6,299,987.00, under the Singapore Institute of Architects' minor works conditions. As required, it provided an unconditional on-demand performance bond issued by Lonpac Insurance Bhd for $629,998.70. COVID-19 restrictions delayed the works, and the claimant served a notification for relief under the COVID-19 (Temporary Measures) Act 2020 (COTMA). The architect issued a completion certificate listing outstanding defective works and a certificate of entitlement to liquidated damages. In April 2023 the claimant was placed under a moratorium to facilitate restructuring.

On 20 July 2023 the church, frustrated with delays and outstanding works, called on the whole bond. Its parish priest said the call covered estimated liquidated damages, outstanding warranties and rectification works including the driveway tarmac and the dome. In HC/OA 876/2023 the claimant sought a declaration that the call was unconscionable and an injunction, or alternatively a reduction to reflect the retention sum of $233,116.67 the church already held. It alleged the liquidated damages ignored s 6(5) of COTMA, that the tarmac and dome works were outside its scope, and that the tarmac quote of $227,040 was excessive. An interim injunction was granted on 30 August 2023 pending the hearing.

Step 2: What the court had to decide

  1. Whether the claimant showed a strong prima facie case that the church acted unconscionably in calling on the performance bond
  2. Whether the amount of the call should be reduced because the church held enough security
  3. Whether an Erinford injunction should be granted pending appeal

Step 3: How the court reasoned

Applying BS Mount Sophia Pte Ltd v Join-Aim Pte Ltd [2012] 3 SLR 352, the threshold of unconscionability is high and requires a strong prima facie case of abuse, unfairness or dishonesty; a mistaken but honest call is legitimate, and the court does not try the merits. The bond was part of the parties' bargain and as good as cash.

On liquidated damages, the claimant knew of the architect's certificate from September 2022, and its footnote was likely stock wording. Whether the architect misapplied s 6(5) of COTMA did not need deciding; under the contract the architect certified independently, so following CEX v CEY and another [2021] 3 SLR 571 any error was not attributable to the church, which had been told by its advisers that valid COTMA claims were accounted for and was not on notice of impropriety. On the tarmac and dome, correspondence showed the claimant had acknowledged it was to carry out those works, and the wide spread among three rough quotes weakened the complaint about the tarmac figure; these were bona fide contractual disputes for the substantive tribunal. There was no evidence on the warranties.

On reduction, the court applied the broad approach in Eltraco International Pte Ltd v CGH Development Pte Ltd [2000] 3 SLR(R) 198. The bond and retention together came to $863,115.37, not out of proportion to the church's bona fide claims of $825,660.00. A claim for additional preliminaries raised after the call was irrelevant. The court also noted material omissions in the claimant's first affidavit, which it accepted were inadvertent.

On the Erinford injunction, an application by letter was allowed. The appeal had a fair chance, but would not be rendered nugatory: the claimant's solvency and investor concerns lay outside the dispute, any excess could be recovered, and prejudice to Lonpac was irrelevant.

From the judgment

“Such an applicant has to convince the court that it is just and fair for the court to assist him in reneging on a contractual promise that he has made.”

[2024] SGHC 5 at [55]

Step 4: The order

Wong Li Kok, Alex JC dismissed the application, finding no unconscionability and no basis to reduce the call, and ordered costs of $22,000 (excluding disbursements) to the church. The later application for an Erinford injunction pending appeal was also dismissed, with costs of $1,500.

Terms in this case

Performance bond
A guarantee, usually from a bank or insurer, given on a contractor's behalf to secure the contractor's performance. If it is payable on demand, the beneficiary can call on it without proving default, and a call is restrained only for fraud or unconscionability.
Unconscionability
In equity, conduct making it unfair to insist on strict legal rights. A contract or gift obtained by exploiting another's poverty, ignorance or weakness may be set aside unless shown fair and reasonable. A call on an on-demand performance bond or standby credit may be restrained where the call is unconscionable — abusive, unfair or dishonest — a narrower, separate test.
Prima facie case
Evidence that, if accepted and not answered, would be enough to establish a claim or charge. In a criminal trial, the court calls on the accused to give a defence only if, at the close of the prosecution's evidence, there is some credible evidence on every element of the charge.
Interim injunction
A temporary court order, made before a dispute is finally decided, that stops a party from doing something or requires it to act until trial or further order. It is generally granted where there is a serious question to be tried and the balance of convenience favours it, and the applicant usually undertakes to pay damages if it proves unjustified.
Liquidated damages
A sum that a contract fixes in advance as payable if a particular breach occurs, such as a daily rate for late completion. It is enforceable if it is a genuine pre-estimate of the likely loss; a sum that is instead a penalty is not enforceable.

Court record

Key facts

Court High Court
Decided
Judge Wong Li Kok, Alex
What the case was about Injunctions, Building and Construction Law

Source: [2024] SGHC 5, High Court, decided — eLitigation. Updated .

Judge

Parties

  • Church of St Teresa Defendant
  • Shanghai Chong Kee Furniture & Construction Pte Ltd Claimant

Counsel

Counsel for the defendant

Statutes cited

COVID-19 (Temporary Measures) Act
Insolvency, Restructuring and Dissolution Act
Restructuring and Dissolution Act

Cases cited (11)

SG (3)
  • [2015] SGHC 57
  • [2017] SGHC 3
  • [2018] SGHC 133
SLR (7)
  • [1995] 2 SLR(R) 262
  • [2000] 1 SLR(R) 117
  • [2000] 3 SLR(R) 198
  • [2001] 1 SLR(R) 458
  • [2003] 1 SLR(R) 394
  • [2012] 3 SLR 352
  • [2021] 3 SLR 571
UK (1)
  • [1974] 2 WLR 749

Cited by (2)

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2024] SGHC 5)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer