Adt Builder Pte. Ltd. v Multi Contracts Pte. Ltd.

District Court

[2026] SGDC 381 · DC/OC 1946/2024 · cites 4 cases

The question

Can a main contractor pass the owner's liquidated damages to a subcontractor whose contract has no completion date?

The answer

No, here. The District Court found no express term passing on the damages, no completion date and no proven delay, dismissed all the main contractor's claims and allowed the subcontractor's counterclaims.

Step 1: What happened

ADT Builder Pte Ltd was the main contractor for a construction project at 18 Sommerville Walk, engaged by the owner on 4 August 2022 under a main contract incorporating the SIA Conditions. Multi Contracts Pte Ltd was its subcontractor for aluminium works. On 17 February 2023 the parties agreed a doors and windows subcontract at a lump sum price of $336,022.50, and on 6 July 2023 a screens and trellises subcontract at a lump sum price of $165,000, each later varied by several undisputed quotations. None of the subcontract documents specified a completion date or a period for completion.

The project's target for its temporary occupation permit (TOP) was 31 December 2023, later extended to 31 January 2024. TOP was obtained only on 5 June 2024. The owner imposed liquidated damages on ADT from 1 February 2024 at $1,200.00 per day. ADT claimed $118,800 from Multi Contracts for 99 days of delay from 1 February 2024 to 9 May 2024, pointing to site meeting minutes, a WhatsApp message from its project manager, and items such as a sliding door, screens and window tracks that it said were finished late. It also claimed $27,582.23 for alleged overpayment, based on its quantity surveyor's remeasurement of the works, and sought to recover adjudication costs it had paid.

Multi Contracts had brought two adjudication applications under the Building and Construction Industry Security of Payment Act 2004, AA221 and AA222, and been paid adjudicated sums of $69,562.78 and $52,113.33 together with 90% of the adjudication costs. It denied liability and counterclaimed $1,417.00 for underpayment and $31,343.96 for its adjudication costs.

Step 2: What the court had to decide

  1. Whether the subcontractor was liable for the liquidated damages the owner imposed for late completion of the project.
  2. Whether the subcontracts were lump sum contracts or remeasurement contracts, and whether the subcontractor had been overpaid.
  3. Which party should bear the costs and disbursements of the two adjudication applications.

Step 3: How the court reasoned

On delay, the court said a main contractor can pass the employer's liquidated damages to a subcontractor only through an express term allocating that liability or under the general law of damages, citing Multiplex Construction Pty Ltd v Sintal Enterprise Pte Ltd [2005] 2 SLR(R) 530. The subcontracts had no such term and no completion date. The pleaded implied term, that the works had to be finished within the main contract period, failed because Multi Contracts was never told the main contract completion date, its staff attended only the parts of site meetings about its own works, and later conduct cannot be used to imply a term, which is judged at the time of contracting.

In any case the court found no delay. Completion means substantial performance, and the items ADT pointed to were minor defects or minor outstanding works. Following Terrenus Energy SL2 Pte Ltd v Attika Interior + MEP Pte Ltd [2023] SGHC 333, ADT had to show the subcontractor's breach was the sole cause of its liability to the owner. It offered no delay analysis or expert evidence, its witnesses admitted that other subcontractors still had outstanding drawings and works in February 2024, and ADT itself approved variations and changed gate designs after 31 January 2024. Its proof of loss was weak: the consultant's recommendation it relied on proposed withholding $199,200 for 166 days, did not show any deduction was actually made, and did not explain the 99 days claimed. Nor was there a basis to pass on the full daily rate to one of several subcontractors.

On the contract type, the subcontracts stated fixed sums, priced each aluminium item individually rather than by a common unit of measurement, were administered and certified on a lump sum basis, and dealt with changes through variation quotations. The remeasurement clauses applied only where the design changed. Both disputed variations were outside the original scope and were not challenged on amount, and the box-up variation did not omit any bars. Applying Diamond Glass Enterprise Pte Ltd v Zhong Kai Construction Co Pte Ltd and another appeal [2022] SGHC(A) 44 on recovering adjudication costs under s 30(4), the court looked at who ultimately succeeded, and Multi Contracts had won both the adjudications and this action.

From the judgment

“As there is no completion date and no contract duration stipulated in the Sub-Contracts, and no basis for implying the Main Contract’s completion date into the Sub-Contracts, the claimant has failed to prove that the defendant was in delay for its works.”

[2026] SGDC 381 at [22]

“If the contracts were on a remeasurement basis, there would have been no requirement for the contracts to provide discrete rates for the various items.”

[2026] SGDC 381 at [45]

“The claims are dismissed and the counterclaims allowed.”

[2026] SGDC 381 at [58]

Step 4: The order

District Judge Chiah Kok Khun dismissed all of ADT's claims and allowed Multi Contracts' counterclaims. The delay claim of $118,800 failed. The subcontracts were held to be lump sum contracts, so the overpayment claim failed; Multi Contracts was entitled to $810 and $1,300 for two disputed variations, and on a final accounting was awarded the net sum of $1,417 for underpayment. ADT's claim for adjudication costs was dismissed and Multi Contracts was awarded its adjudication costs and disbursements of $31,343.96. Parties were directed to file submissions on costs, limited to five pages, within 14 days.

The order in the court's words

Claim dismissed

“The claims are dismissed and the counterclaims allowed.”

Source: [2026] SGDC 381, District Court, decided 26 November 2026. Read directly from the judgment.

Terms in this case

Counterclaim
A claim that a defendant brings against the claimant in the same proceedings, rather than starting a separate action. The court can decide the claim and the counterclaim together.
Expert evidence
Opinion evidence from a person with specialised knowledge gained through training, study or experience, given to help the court on matters outside ordinary knowledge. Under the Evidence Act 1893 such opinion is relevant, but the court decides how much weight to give it, and an expert owes a duty to assist the court impartially.
Express term
A term of a contract that the parties have actually stated, whether orally or in writing, as distinct from an implied term, which the law, custom or the court reads into the contract to fill a gap the parties left.
Implied term
A term not expressly stated in a contract but treated as part of it, either because the law, a statute or custom implies it into all contracts of that kind, or because it is needed to fill a gap the parties did not foresee.
Liquidated damages
A sum that a contract fixes in advance as payable if a particular breach occurs, such as a daily rate for late completion. It is enforceable if it is a genuine pre-estimate of the likely loss; a sum that is instead a penalty is not enforceable.
Security of payment
The scheme under the Building and Construction Industry Security of Payment Act that gives those who carry out construction work or supply goods or services for it a right to progress payments and a fast adjudication process when payment is disputed.

Court record

Key facts

Court District Court
Decided
Judge Chiah Kok Khun
What the case was about Building and Construction Law
Outcome Claim dismissed

Source: [2026] SGDC 381, District Court, decided — eLitigation. Updated .

Judge

Parties

Statutes cited

Cases cited (4)

SLR (1)
  • [2005] 2 SLR(R) 530

Related cases

Other Singapore judgments on the same subject, most closely matched first.

Read the full judgment

The judgment itself is on the official Singapore Courts portal.

Read on eLitigation

Source: eLitigation ([2026] SGDC 381)

This page sets out what the court decided, for learning. It is information, not legal advice. Disclaimer